INSP-Final Inspection | 9/1/2006 | 9/5/2006 | 9/5/2006 | A | PASS |
Forrest France
|
|
|
Required corrections have been made, fire sprinkler permit finaled.
|
INSP-Final Inspection | 8/30/2006 | 9/1/2006 | 9/1/2006 | A | PART |
Forrest France
|
|
|
Final field inspection is satisfactory pending proper coverage at the level of exit discharge for two stairways.
|
INSP-Sprinkler Rough-in/Hydro | 8/21/2006 | 8/22/2006 | 8/22/2006 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in is passed. Piping in the office areas is ok to cover. Two esfr heads on the east side of the electrical room are overspaced. Earthquake bracing on the mains needs finished up. Above ground hydro test passed.
|
INSP-Sprinkler Rough-in | 8/8/2006 | 8/9/2006 | 8/9/2006 | P | PASS |
Troy Cobbley
|
|
|
Riser room and the electrical room piping rough-ins are passed and the piping can be covered.
|
INSP-Sprinkler Rough-in | 7/17/2006 | 7/18/2006 | 7/18/2006 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping as marked on the plans that is located above the ceilings is ok to cover.
|
Plan assigned to (Bill) | 5/3/2006 | | 5/11/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/3/2006 | | 5/11/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/11/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/11/2006 | | 5/11/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/11/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/11/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/11/2006 | | 5/11/2006 | | DONE |
|
|
|
|
Application received | | | 5/3/2006 | | |
|
|
|
|