Information based on query as of Saturday, August 17, 2024.
Permit Information
Permit NumberFIR06-00346
StatusFinaled
Name MICRON TECHNOLOGY INC FP
Site Address 8000 S FEDERAL WAY
Project NameSPR MICRON #24C F4 FAB
Customer NumberC8790
ePlanReview 
Description
MICRON BUILDING #24C - (C8790) - To install fire sprinkler protection under the raised floor of new 100 lineal feet of 4'-6" and 8'-0" wide by 4'-0" deep reinforced concrete equipment trenches at the subfab and the cleanroom ceilings, for the remodel of Fab 4A in Building 24C to accommodate new tool sizes and equipment. The fire sprinkler work relate to subfloor trench work, reconstruction of fab clean walls, hepa filter ceiling grids. This work is located in Building #24C between grid lines #18 & 25 and #D & F at an approximate 6,675-ft/2 of the subfab, a 10,280-ft/2 area of the main floor fabrication area and 10,190-ft/2 of the interstitial space. This fire protection work shall comply with the IFC 2003 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD06-00475.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/22/20069/27/20069/28/2006PPASS
DetailsForrest France
Fire sprinkler final inspection passed, permit finaled.
INSP-Sprinkler Rough-in/Hydro9/11/20069/12/20069/12/2006APART
DetailsForrest France
Re-test of hydrostatic for the underfloor system passed.
INSP-Sprinkler Rough-in/Hydro9/5/20069/8/20069/8/2006AFAIL
DetailsTroy Cobbley
Hydro test failed. Guage appeared to have lost 2-3 psi from 10:15am to 12:15pm.
INSP-Sprinkler Rough-in/Hydro8/16/20068/17/20068/17/2006APART
DetailsForrest France
Rough-in for the west underfloor area and OH for the 1st and 2nd levels is acceptable, Hydrostatic test for a portion of these systems at the two 4" main trees and one 3" passed.
Plan resubmittals received  7/24/2006 DONE
DetailsBill Alexander
Sprinkler Plan Check7/21/2006 7/24/2006 PASS
DetailsBill Alexander
Plan assigned to (Bill)5/23/2006 6/24/2006 DONE
DetailsBill Alexander
Sprinkler Plan Check5/23/2006 5/25/2006 FAIL
DetailsBill Alexander
Re-Submittals Of The Following Items Are Required:
1. Section view "A", FP.4.1 shows the cleanroom level pendant heads are incorporating Flexhead® system. It is also noted that all armover, drops (including the Flexhead® piping) is 1¼"?
a. Please provide data submittals addressing these Flexhead® listed units and include identification relating to the lengths incorporating on the project.
b. Reverify and revise calculation addressing the correct (sized) and listed friction loss information for those lengths installing, and resubmit.

2. Hydraulic Calculation "Raised Floor" and "Cleanroom Ceiling" plans conflict or do not correlate. Not all notes on the plans and calculations are found. Basically starting from Node #1 through #4. Raised floor base of riser starts at node #2 and Cleanroom starts at #5? Nodes 5 and 6 calcs conflict with FP.6.0 with the same? Cannot determine if these areas are piped off the same system, since the nodes do not correlate. If separate riser, then identify each separately with each area protecting. If the same then correlate the nodes so they do not conflict. Please reverify and clarify your design and calculations so they correlate, etc.

3. Provide plan clarification with correct piping for draining requirements meeting NFPA 13-8.15.2.5 on the under-floor.
PLANS/APPL TAKEN TO FRONT DESK  5/25/2006 DONE
DetailsBill Alexander
Permit Ready to Issue  5/25/2006 DONE
per Bill ok to issue with corrections
Issue and Print Permit  5/25/2006 DONE
Application received  5/9/2006 DONE
This permit was created on the web by Paul Marcolina