INSP-Final Inspection | 1/31/2007 | 2/1/2007 | 2/1/2007 | P | PASS |
Forrest France
|
|
|
Per field inspection by B. Johnson, the fire sprinkler installation is satisfactory. Noted several areas at tenant spaces where storage heights exceed the maximum allowable.
|
INSP-Final Inspection | 1/30/2007 | 1/30/2007 | 1/30/2007 | P | NR |
Forrest France
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
INSP-Sprinkler Rough-in/Hydro | 11/13/2006 | 11/13/2006 | 11/13/2006 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test for overhead sprinkler piping from the Needle Works to the Cookie Lady has passed. This hydro test did not include the canopy.
|
Issue and Print Permit | | | 6/1/2006 | | |
|
|
|
|
Telephone call | | | 5/23/2006 | | DONE |
|
|
|
tlk to viking ###-#### that permit and fees are ready to be picked up
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/22/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/22/2006 | | 5/22/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/22/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 5/11/2006 | | 5/22/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/22/2006 | | |
|
|
|
|
Sprinkler Plan Check | 5/22/2006 | | 5/22/2006 | | PASS |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 5/11/2006 | | 5/17/2006 | | FAIL |
Bill Alexander
|
|
|
|
Telephone call | | | 5/17/2006 | | DONE |
|
|
|
Spoke with Diane and told her that the set of plans needs picked up for corrections clarifications///5/17/06 @ 9:05am BAS
|
Application received | | | 5/11/2006 | | |
|
|
|
|