INSP-Final Inspection | 6/5/2006 | 6/5/2006 | 6/5/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler passed final inspection, permit finaled.
|
INSP-Final Inspection | 5/19/2006 | 5/22/2006 | 5/22/2006 | A | NR |
Forrest France
|
|
|
###-#### Final pending ceiling tile installation and escutcheons at heads.
|
INSP-Sprinkler Rough-in | 5/19/2006 | 5/22/2006 | 5/22/2006 | A | PART |
Forrest France
|
|
|
Need to provide vertical restraint at the end hangers per review notes, the remainder of overhead work is acceptable.
|
Issue and Print Permit | | | 5/19/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 5/16/2006 | | 5/17/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/16/2006 | | 5/17/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/17/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/17/2006 | | 5/17/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/17/2006 | | 5/17/2006 | | DONE |
|
|
|
|
Telephone call | | | 5/17/2006 | | DONE |
|
|
|
tlk to jim daves - ###-#### that permit and fees are ready to be picked up
|
Telephone call | | | 5/17/2006 | | DONE |
|
|
|
tlk to jim daves - ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 5/17/2006 | | DONE |
|
|
|
|
Case Summary | | | 5/16/2006 | | DONE |
|
|
|
|
Application received | | | 5/16/2006 | | |
|
|
|
|