INSP-Final Inspection | 8/14/2006 | 8/15/2006 | 8/15/2006 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test on both dry systems passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/9/2006 | 8/10/2006 | 8/10/2006 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/4/2006 | 8/8/2006 | 8/8/2006 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Still need to fire caulk penatrations at riser room, add earth quaking in dock area, finish inspectors test piping. No pressure testing or items usually associated with the final have been done yet.
|
Issue and Print Permit | | | 6/2/2006 | | |
|
|
|
|
Plan assigned to (Bill) | 5/30/2006 | | 6/1/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/30/2006 | | 6/1/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/1/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/1/2006 | | 6/1/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/1/2006 | | DONE |
|
|
|
|
Telephone call | | | 6/1/2006 | | DONE |
|
|
|
lft vm with debest ###-#### that permit and fees are ready to be picked up
|
Application received | | | 5/30/2006 | | |
|
|
|
|