INSP-Final Inspection | 8/17/2006 | 8/17/2006 | 8/18/2006 | P | PASS |
Troy Cobbley
|
|
|
Permit is finaled
|
INSP-Sprinkler Rough-in | 7/26/2006 | 7/27/2006 | 7/27/2006 | A | FAIL |
Troy Cobbley
|
|
|
See approved plans for locations of needed corrections. They include sidewall heads mounted too low, head overspaced in bedroom, hanger ring unattached and missing piping.
|
CHANGE STATUS TO (ISS) | | | 7/26/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 7/18/2006 | | 7/25/2006 | | DONE |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/18/2006 | | 7/25/2006 | | PASS |
Bill Alexander
|
|
|
|
Permit Ready to Issue | | | 7/25/2006 | | DONE |
|
|
|
|
Telephone call | | | 7/25/2006 | | DONE |
|
|
|
spoke to tim@###-####/told permit was ready/permit#, project name & address, and fee
|
Plan resubmittals received | | | 7/18/2006 | | |
|
|
|
|
Issue permit | | | 6/6/2006 | | |
|
|
|
|
Inspection Record Card- Fire | 6/5/2006 | | 6/5/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/31/2006 | | 6/5/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Plan assigned to (Scott) | 5/31/2006 | | 6/5/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/5/2006 | | DONE |
|
|
|
|
Application received | | | 5/31/2006 | | |
|
|
|
|
Inspection Record Card- Fire | 6/5/2006 | | | | |
|
|
|
|