INSP-Final Inspection | 9/15/2006 | 9/15/2006 | 9/15/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 9/11/2006 | 9/12/2006 | 9/12/2006 | A | PART |
Forrest France
|
|
|
Rough-in corrections have been completed, OH is okay for cover at the drop ceiling areas.
|
INSP-Final Inspection | 9/11/2006 | 9/11/2006 | 9/11/2006 | P | NR |
Forrest France
|
|
|
Project is not complete for final, rough-in inspection failed.
|
INSP-Sprinkler Rough-in | 9/11/2006 | 9/11/2006 | 9/11/2006 | P | FAIL |
Forrest France
|
|
|
One head is blocked by a light fixture in the NE hallway, heads are overspaced in the north hall at two locations, work room head is overspaced off one adjacent wall, overspacing at the west side of the teller area, inspection concluded at this time due to the number of defficiencies-east side of the TI area not inspected today.
|
INSP-Sprinkler Rough-in | 7/17/2006 | 7/17/2006 | 7/17/2006 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping as marked on the plans located over the hardlid areas on the west half of the first floor are ok to cover.
|
Inspection Record Card- Fire | 6/6/2006 | | 6/6/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/6/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/2/2006 | | 6/2/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Plan assigned to (Scott) | 6/2/2006 | | 6/2/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2006 | | DONE |
|
|
|
|
Application received | | | 6/1/2006 | | |
|
|
|
|
Case Summary | | | 6/1/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 6/1/2006 | | | | |
|
|
|
|