INSP-Final Inspection | 3/13/2007 | 3/13/2007 | 3/13/2007 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 3/12/2007 | 3/12/2007 | 3/12/2007 | P | FAIL |
Troy Cobbley
|
|
|
Need to provide forward flush and the test/drain as per the drawings.
|
INSP-Sprinkler Rough-in/Hydro | 10/4/2006 | 10/5/2006 | 10/5/2006 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/3/2006 | 10/3/2006 | 10/4/2006 | P | FAIL |
Troy Cobbley
|
|
|
Above ground hydro test failed
|
INSP-Sprinkler Rough-in/Hydro | 10/2/2006 | 10/2/2006 | 10/2/2006 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed but the overhead hydro test failed.
|
INSP-Supply line flush | 8/28/2006 | 8/29/2006 | 8/29/2006 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
Telephone call | | | 6/12/2006 | | DONE |
|
|
|
tlk to brodie that permit and fees are ready to be picked up
|
Issue and Print Permit | | | 6/12/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/9/2006 | | 6/9/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Plan assigned to (Scott) | 6/7/2006 | | 6/9/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/9/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/9/2006 | | 6/9/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/9/2006 | | DONE |
|
|
|
|
Application received | | | 6/1/2006 | | |
|
|
|
|
Case Summary | | | 6/1/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 6/1/2006 | | | | |
|
|
|
|