INSP-Final Inspection | 8/17/2006 | 8/21/2006 | 8/21/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/15/2006 | 8/17/2006 | 8/17/2006 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave hanniman's permission until the dry system for the outside canopy has been completed.
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 8/17/2006 | | |
|
|
|
|
INSP-Alarm Testing | 8/14/2006 | 8/15/2006 | 8/15/2006 | A | DONE |
Troy Cobbley
|
|
|
Sound test passed today for the audio/visual devices. Four problems that need addressed are the strobe in the northeast service corridor is overspaced, the sound level in the storage room adjacent to the archery ranch is too low and both ceiling mount a/v's in the fly shop are not at the correct candella. All sprinkler items need addressed and the two horns in the fish tank/mechanical room need installed.
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 8/15/2006 | | |
|
|
|
|
INSP-Alarm Testing | 8/14/2006 | 8/14/2006 | 8/14/2006 | P | DONE |
Troy Cobbley
|
|
|
Duct detector testing passed today.
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 8/14/2006 | | |
|
|
|
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 8/14/2006 | | |
|
|
|
|
INSP-Final Inspection | 8/11/2006 | 8/11/2006 | 8/11/2006 | P | FAIL |
Troy Cobbley
|
|
|
The testing today included the system smoke detectors, supervision of the NAC panels and sound levels of the notification devices. The sound levels appeared to be inadequate but per Brian the wrong scale was used. The sound levels will be reverified monday.
|
Override - Parcel Holds | | | 8/11/2006 | | |
|
|
|
|
INSP-Final Inspection | 8/9/2006 | 8/10/2006 | 8/10/2006 | P | FAIL |
Troy Cobbley
|
|
|
The only items tested and passed today are the main fire alarm panel, voice evac panel, remote fire alarm control panel in the security office and the two NAC panels. Also tested was the smoke detector in the security office.
|
Plan assigned to (Mary) | 6/5/2006 | | 7/5/2006 | | DONE |
|
|
|
|
Alarm Plan Check | 6/29/2006 | | 7/5/2006 | | PASS |
Troy Cobbley
|
|
|
Approved with comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/5/2006 | | 7/5/2006 | | DONE |
|
|
|
|
Telephone call | | | 7/5/2006 | | |
|
|
|
called ###-#### and left voicemail for Charlie that permit is ready and fee
|
Permit Ready to Issue | | | 7/5/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/5/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/29/2006 | | |
|
|
|
|
Alarm Plan Check | | | 6/26/2006 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Charlie Bayne
|
Plan resubmittals received | | | 6/19/2006 | | |
|
|
|
|
Alarm Plan Check | | | 6/13/2006 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Charlie Bayne
|
Application received | | | 6/5/2006 | | |
|
|
|
|
Case Summary | | | 6/5/2006 | | DONE |
|
|
|
|