INSP-Final Inspection | 2/23/2007 | 2/26/2007 | 2/26/2007 | P | PASS |
Forrest France
|
|
|
Corrections are complete, fire sprinkler permit finaled.
|
INSP-Final Inspection | 2/22/2007 | 2/23/2007 | 2/23/2007 | P | NR |
Forrest France
|
|
|
Per phone call from the contractor, the required repairs have not yet been made.
|
INSP-Final Inspection | 2/21/2007 | 2/22/2007 | 2/22/2007 | P | FAIL |
Forrest France
|
|
|
The outside bell failed to function upon waterflow. UG flush completed okay.
|
INSP-Final Inspection | 1/29/2007 | 1/30/2007 | 1/30/2007 | P | NR |
Forrest France
|
|
|
Contact is James @ ###-####. Thanks Phone #: ###-#### Contractor is not ready per phone call, pending UG flush.
|
INSP-Final Inspection | 1/25/2007 | 1/29/2007 | 1/29/2007 | P | NR |
Forrest France
|
|
|
Noted the UG supply line flush must be completed prior to overhead final.
|
INSP-Final Inspection | 1/4/2007 | 1/5/2007 | 1/5/2007 | A | CANC |
Forrest France
|
|
|
Please call Brian one hour before arriving.
His number is ###-####. Thanks Phone #: ###-#### Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 7/28/2006 | 7/31/2006 | 7/31/2006 | P | PART |
Forrest France
|
|
|
OH rough-in is okay to cover, noted two sprinkler heads in the basement which will require relocation for proper spacing and coverage.
|
INSP-Sprinkler Rough-in | 7/27/2006 | 7/28/2006 | 7/28/2006 | A | FAIL |
Forrest France
|
|
|
Relocate one head at basement closet, one drop is overspaced at basement room, tenting is not adequate at three riser locations on swing joints and is missing above branch lines in the family room, discussed freeze protection for lines in the garage area.
|
Sprinkler Plan Check | 7/21/2006 | | 7/27/2006 | | PASS |
Bill Alexander
|
|
|
|
Miscellaneous action | | | 7/27/2006 | | DONE |
|
|
|
Took approved plans to permit desk. 2nd Review, no fee.
|
Telephone call | | | 7/27/2006 | | DONE |
|
|
|
spoke to lilly@###-####/told permit was ready, permit#, address, project name, and no fee for resubmittal
|
Plan resubmittals received | | | 7/21/2006 | | |
|
|
|
|
Issue and Print Permit | | | 7/20/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 6/27/2006 | | 7/19/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/22/2006 | | 7/19/2006 | | PART |
Bill Alexander
|
|
|
Re-Submittals Of The Following Items Are Required:
1. The upstairs single head operation is not accepted since two heads shall be included in the calcs. Revise and resubmit offering the most demanding verification of system design. Include final head analysis report with the calcs.
2. Provide a final head analysis report for test area #2.
3. A domestic and sprinkler (combination control) shall be connected upstream of the fire sprinkler and domestic takeoff, (no exceptions), which is required for monitoring of system per NFPA 13D-A.6.2(a), A.6.3(a) and included the valve in the calculations.
4. Correct Riser Key Notes:
a. #1,
b. #1A pipe size,
c. #3 (reference requirements in item #3 above).
5. Riser installation detail is incomplete. Provide added requirements for exposed CPVC RISER piping and fittings, which does not stop at a pendant sprinkler with 1'-0" of the riser. This information is not included in the (partial/incomplete) CPVC pipe data submittals provided.
6. Garage (barrier protection) sprinklers may be susceptible to freeze damage. Provide clarification as to how this will be prevented.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/19/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/19/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/19/2006 | | 7/19/2006 | | DONE |
|
|
|
|
Telephone call | | | 7/19/2006 | | DONE |
|
|
|
spoke to lilly@###-####/told permit was ready, permit#, project name, and fee
|
Miscellaneous action | | | 6/28/2006 | | DONE |
|
|
|
Early Start request from Shiloh approved and faxed back to contractor.
|
Application received | | | 6/27/2006 | | |
|
|
|
|
Case Summary | | | 6/27/2006 | | DONE |
|
|
|
|