INSP-Final Inspection | 11/8/2006 | 11/9/2006 | 11/9/2006 | A | PASS |
Forrest France
|
|
|
Final inspection was completed and passed on 10/20/06 by T. Cobbley, permit finaled.
|
Plan assigned to (Mary) | 7/5/2006 | | 11/6/2006 | | PASS |
|
|
|
11/6/2006 16:39:02 SLR - activity updated through activity FIRA22 from case FIR06-00137.
|
INSP-Alarm Testing | 10/19/2006 | 10/20/2006 | 10/20/2006 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 10/19/2006 | 10/19/2006 | 10/19/2006 | P | FAIL |
Troy Cobbley
|
|
|
Started test but found that the signal descriptions have not been set up. Testing of devices stopped. All notification devices inspected and tested.
|
INSP-Final Inspection | 10/17/2006 | 10/18/2006 | 10/18/2006 | A | CANC |
Troy Cobbley
|
|
|
Phil wanted to reschedule for tommorrow
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/31/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/31/2006 | | 7/31/2006 | | DONE |
|
|
|
|
Telephone call | | | 7/31/2006 | | DONE |
|
|
|
spoke to phil@###-####/told permit was ready, permit#, project name & address, and fee
|
Issue and Print Permit | | | 7/31/2006 | | DONE |
|
|
|
|
Alarm Plan Check | 7/31/2006 | | 7/28/2006 | | PASS |
|
|
|
Plan reviewed 7/16/06 and accepted per telcon 7/28 with FV.
|
Miscellaneous action | | | 7/11/2006 | | |
|
|
|
Sent to floyd Varley.
|
Application received | | | 7/5/2006 | | |
|
|
|
|