INSP-Final Inspection | 7/11/2007 | 7/12/2007 | 7/12/2007 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 7/10/2007 | 7/11/2007 | 7/11/2007 | P | FAIL |
Troy Cobbley
|
|
|
The fire dept connection is mounted too high and not all of the ceiling tile has been installed. The forward flush passed.
|
Issue and Print Permit | | | 7/3/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/26/2007 | | 7/2/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/2/2007 | | 7/2/2007 | | DONE |
|
|
|
|
Telephone call | | | 7/2/2007 | | DONE |
|
|
|
lft ms for john ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 7/2/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/15/2007 | | DONE |
|
|
|
received three copies of sheets FP-1 FP-2 sprinkler data, calculations and bracing placed plans in bin for pickup.rad
|
Plan assigned to (SAM) | 3/15/2007 | | 3/15/2007 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 2/15/2007 | 2/15/2007 | 2/15/2007 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/14/2007 | 2/14/2007 | 2/14/2007 | P | PASS |
Troy Cobbley
|
|
|
underground hydro test passed
|
INSP-Supply line flush | 2/8/2007 | 2/9/2007 | 2/9/2007 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
Issue and Print Permit | | | 11/15/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/26/2006 | | 10/26/2006 | | DONE |
|
|
|
|
Telephone call | | | 10/26/2006 | | |
|
|
|
lft ms for tim fleming ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/26/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/25/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 7/14/2006 | | 10/25/2006 | | PASS |
|
|
|
10/25/2006 16:23:36 SLR - activity updated through activity FIRA22 from case FIR06-00518.
|
Sprinkler Plan Check | | | 10/20/2006 | | PASS |
|
|
|
3rd revision approved subject to comments, by B. Johnson.
|
Telephone call | | | 10/5/2006 | | |
|
|
|
Faxed Copy of Denied Review to Applicant
|
Sprinkler Plan Check | | | 9/30/2006 | | FAIL |
|
|
|
Plans review by Brian Johnson Failed 9/30/06
|
Plan resubmittals received | | | 9/15/2006 | | |
|
|
|
|
Sprinkler Plan Check | | | 9/12/2006 | | FAIL |
|
|
|
Resubmittal reviewed and denied by B. Johnson. Hyd. cover sheets and summary reports do not correspond with each other and also do not correspond with the plans FP-2 hyd. placard. Review comments faxed to Commercial Fire.
|
Plan resubmittals received | | | 8/29/2006 | | |
|
|
|
|
Sprinkler Plan Check | | | 8/8/2006 | | FAIL |
|
|
|
Plans reviewed by BJ; denied. One set taken to front counter for pickup by contracotr.
|
Application received | | | 7/14/2006 | | |
|
|
|
|
Case Summary | | | 7/14/2006 | | DONE |
|
|
|
|