Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR06-00536
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 6017 W FAIRVIEW AVE
Project NameLes Schwab Warehouse
Customer Number 
ePlanReview 
Description
Scope of Work: Run a new 8" fire service through a utility vault with a new back flow deice and then up and into an existing 5,000 ft/2 single story warehouse. A Peerless Fire Pump Unit / Riser will be installed. The overhead piping will consist of a 4" wet fire sprinkler system, protecting Rack tire storage to 15'-0", incorporating EFSR heads. The water supply will be connected to a new Peerless, 65 psi/1000 gpm rated electric booster pump, and a (current) United Water supply of 60 static, 1,750 gpm flow @ 20 psi. The building is fully fire sprinklered with an unlimited area designation. Any racking over 15'-0" will require separate plans and permits prior to installation. This permit is not attached to a building permit; proposed work is as a result of a fire dept inspection report.Revised Scope of Work:
The revision of the original scope of work includes relocating the FDC to the NW corner of the Bldg. as indicated on sheet FP-101. The new location meets code.
Submittals Of The Following Items Are Required:
The outline of the structure is not clearly defined. FP-101 & FP-102
(Revised & Clarified 11/16/2006)
The notes regarding the scope of work need to be clarified. FP-101 & FP-102
(Revised & Clarified 11/16/2006)
Please provide the notes that pertain to the Fire Pump Schematic.
(A sheet FP-3 has been submitted for clarity 11/16/2006)
Please provide Warehouse area ft/2 and construction type. FP-100
(Revised & Clarified 11/16/2006)
Provide a trapeze detail. Include the design modulus.
(Revised & Clarified 11/16/2006)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/11/20075/14/20075/14/2007APASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection5/9/20075/11/20075/11/2007AFAIL
DetailsTroy Cobbley
The fire pump acceptance test passed. Fire sprinkler rough-in passed. Contractor supplied certification that the fire pump package had been hydro tested. The backflow was certified as I waited. To final the project the signage on the riser room door needs to be installed and the orfice to test the flow switch needs to be provided. The ventilation and drainage as is will be acceptable. Emergency lighting has been provided.
INSP-Sprinkler Rough-in5/2/20075/2/20075/2/2007PPASS
DetailsTroy Cobbley
hydro test of the fdc passed.
INSP-Sprinkler Rough-in/Hydro4/26/20074/27/20074/27/2007APASS
DetailsTroy Cobbley
Hydro test of the overhead piping is passed. Fire pump and fdc stills needs hydro testing
CHANGE STATUS TO (ISS)  4/26/2007  
changed to issued status no fee due
PLANS/APPL TAKEN TO FRONT DESK  4/25/2007 DONE
Inspection Record Card- Fire4/25/2007 4/25/2007 DONE
Telephone call  4/25/2007 DONE
lft vm with george lawatch ###-#### that permit and no fee is ready to be picked up
Permit Ready to Issue  4/25/2007  
Sprinkler Plan Check4/17/2007 4/23/2007 PASS
Revised Plans are approved 04/23/2007 by Bryan Johnson
Plan resubmittals received  4/17/2007  
INSP-Supply line flush4/12/20074/13/20074/13/2007APASS
DetailsTroy Cobbley
Underground flush and hydro test passed.
INSP-Supply line flush4/10/20074/11/20074/12/2007APASS
DetailsTroy Cobbley
Underground supply line is ok to cover. The underground vault has been deleted as well as the remote FDC. I notified the fire sprinkler contractor that approval is required for the relocation of the FDC.
INSP-Supply line flush4/10/20074/11/20074/11/2007PCANC
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 4/10/2007 at 8:22:07 AM. Contact: ###-####.
INSP-Supply line flush4/10/20074/12/20074/10/2007ACANC
DetailsTroy Cobbley
###-#### George Inspection cancelled from web by: Patricia Smith
Plan resubmittals received  2/27/2007 PASS
Received fax for plan modification of FDC location. Approved by BJ. Redistributed directly to contractor. No fee.
Miscellaneous action  2/1/2007 DONE
Gave plans to Viking (Tyson)2/1/07
Sprinkler Plan Check2/1/2007 2/1/2007 PASS
Plans are acceptable per fire sprinkler reviewer
PLANS/APPL TAKEN TO FRONT DESK  2/1/2007  
Inspection Record Card- Fire2/1/2007 2/1/2007 DONE
Permit Ready to Issue  2/1/2007 DONE
(F) Reprint permit  2/1/2007 DONE
CHANGE STATUS TO (ISS)  2/1/2007 DONE
Plan assigned to (Bill)7/19/2006 2/1/2007 PASS
2/1/2007 14:59:01 SJA - activity updated through activity FIRA22 from case FIR06-00536.
Sprinkler Plan Check  11/20/2006 FAIL
Reviewed by B. Johnson. Resubmittal requirements were emailed to Viking by B.J. Plans are avaialble for pick-up if desired by contractor.
Plan resubmittals received  10/31/2006 DONE
Telephone call  10/10/2006 DONE
Spoke with George at Viking re status of resub. He said plans are being re-drawn to show a new location for the booster FP. Refered me to Viking Proj Mgr. Al Chabre, ###-#### for details. I called Al, they plan to resubmit next week; plan to move the pump to a new room to be created inside the building due to Planning regulations; fire pump is on order for December delivery.
Case Summary  10/10/2006  
Case Summary  10/10/2006  
Sprinkler Plan Check8/15/2006 8/16/2006 FAIL
Review of 8/15/06 resubmittal by B. Johnson. Review comments faxed to Viking 8/21.
Application received  7/19/2006  
Case Summary  7/19/2006 DONE