INSP-Final Inspection | 5/11/2007 | 5/14/2007 | 5/14/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 5/9/2007 | 5/11/2007 | 5/11/2007 | A | FAIL |
Troy Cobbley
|
|
|
The fire pump acceptance test passed. Fire sprinkler rough-in passed. Contractor supplied certification that the fire pump package had been hydro tested. The backflow was certified as I waited. To final the project the signage on the riser room door needs to be installed and the orfice to test the flow switch needs to be provided. The ventilation and drainage as is will be acceptable. Emergency lighting has been provided.
|
INSP-Sprinkler Rough-in | 5/2/2007 | 5/2/2007 | 5/2/2007 | P | PASS |
Troy Cobbley
|
|
|
hydro test of the fdc passed.
|
INSP-Sprinkler Rough-in/Hydro | 4/26/2007 | 4/27/2007 | 4/27/2007 | A | PASS |
Troy Cobbley
|
|
|
Hydro test of the overhead piping is passed. Fire pump and fdc stills needs hydro testing
|
CHANGE STATUS TO (ISS) | | | 4/26/2007 | | |
|
|
|
changed to issued status no fee due
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/25/2007 | | 4/25/2007 | | DONE |
|
|
|
|
Telephone call | | | 4/25/2007 | | DONE |
|
|
|
lft vm with george lawatch ###-#### that permit and no fee is ready to be picked up
|
Permit Ready to Issue | | | 4/25/2007 | | |
|
|
|
|
Sprinkler Plan Check | 4/17/2007 | | 4/23/2007 | | PASS |
|
|
|
Revised Plans are approved 04/23/2007 by Bryan Johnson
|
Plan resubmittals received | | | 4/17/2007 | | |
|
|
|
|
INSP-Supply line flush | 4/12/2007 | 4/13/2007 | 4/13/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground flush and hydro test passed.
|
INSP-Supply line flush | 4/10/2007 | 4/11/2007 | 4/12/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line is ok to cover. The underground vault has been deleted as well as the remote FDC. I notified the fire sprinkler contractor that approval is required for the relocation of the FDC.
|
INSP-Supply line flush | 4/10/2007 | 4/11/2007 | 4/11/2007 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 4/10/2007 at 8:22:07 AM. Contact: ###-####.
|
INSP-Supply line flush | 4/10/2007 | 4/12/2007 | 4/10/2007 | A | CANC |
Troy Cobbley
|
|
|
###-#### George Inspection cancelled from web by: Patricia Smith
|
Plan resubmittals received | | | 2/27/2007 | | PASS |
|
|
|
Received fax for plan modification of FDC location. Approved by BJ. Redistributed directly to contractor. No fee.
|
Miscellaneous action | | | 2/1/2007 | | DONE |
|
|
|
Gave plans to Viking (Tyson)2/1/07
|
Sprinkler Plan Check | 2/1/2007 | | 2/1/2007 | | PASS |
|
|
|
Plans are acceptable per fire sprinkler reviewer
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2007 | | |
|
|
|
|
Inspection Record Card- Fire | 2/1/2007 | | 2/1/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/1/2007 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/1/2007 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/1/2007 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 7/19/2006 | | 2/1/2007 | | PASS |
|
|
|
2/1/2007 14:59:01 SJA - activity updated through activity FIRA22 from case FIR06-00536.
|
Sprinkler Plan Check | | | 11/20/2006 | | FAIL |
|
|
|
Reviewed by B. Johnson. Resubmittal requirements were emailed to Viking by B.J. Plans are avaialble for pick-up if desired by contractor.
|
Plan resubmittals received | | | 10/31/2006 | | DONE |
|
|
|
|
Telephone call | | | 10/10/2006 | | DONE |
|
|
|
Spoke with George at Viking re status of resub. He said plans are being re-drawn to show a new location for the booster FP. Refered me to Viking Proj Mgr. Al Chabre, ###-#### for details. I called Al, they plan to resubmit next week; plan to move the pump to a new room to be created inside the building due to Planning regulations; fire pump is on order for December delivery.
|
Case Summary | | | 10/10/2006 | | |
|
|
|
|
Case Summary | | | 10/10/2006 | | |
|
|
|
|
Sprinkler Plan Check | 8/15/2006 | | 8/16/2006 | | FAIL |
|
|
|
Review of 8/15/06 resubmittal by B. Johnson. Review comments faxed to Viking 8/21.
|
Application received | | | 7/19/2006 | | |
|
|
|
|
Case Summary | | | 7/19/2006 | | DONE |
|
|
|
|