INSP-Final Inspection | 5/30/2007 | 5/31/2007 | 5/31/2007 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled, noted project modification to not complete the chest room as indicated on plans, upright protection is provided for the interm.
|
INSP-Sprinkler Rough-in | 7/31/2006 | 8/1/2006 | 8/1/2006 | A | PART |
Forrest France
|
|
|
OH inspection for the 3 heads in the RAD room only as marked on approved plans is acceptable.
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 7/31/2006 | | |
|
|
|
|
Plan assigned to (Bill) | 7/18/2006 | | 7/28/2006 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 7/19/2006 | | 7/28/2006 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 7/28/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 7/28/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 7/28/2006 | | |
|
|
|
|
Issue and Print Permit | | | 7/28/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 7/28/2006 | | |
|
|
|
|
Inspection Record Card- Fire | 7/28/2006 | | 7/28/2006 | | DONE |
|
|
|
|
Miscellaneous action | | | 7/25/2006 | | DONE |
|
|
|
picked up failed plans
|
Application received | | | 7/21/2006 | | |
|
|
|
|
Sprinkler Plan Check | 7/18/2006 | | 7/21/2006 | | FAIL |
Bill Alexander
|
|
|
Fire permit associated as submitted was finaled and a new fire permit assigned. Plans are incomplete, confusing and work is unrecognizable since "circled" areas go off the page? The locations of heads thus, are not specifically outlined on the plan/s and work area cannot be defined.
|
Miscellaneous action | | | 7/21/2006 | | DONE |
|
|
|
Designer is on vacation. Took failed documents to permit desk for returning, corrections, clarification.
|
Telephone call | | | 7/21/2006 | | DONE |
|
|
|
left message for brodie/resubmittal failed review and that papers can be picked up
|