INSP-Final Inspection | 12/21/2006 | 12/22/2006 | 12/22/2006 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 12/21/2006 | 12/21/2006 | 12/21/2006 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/19/2006 | 12/20/2006 | 12/20/2006 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro test failed.
|
INSP-Sprinkler Rough-in | 12/7/2006 | 12/8/2006 | 12/8/2006 | A | PASS |
Troy Cobbley
|
|
|
Gave approved for piping to be covered above hardlids next to pool at the extended coverage heads and in the east stairwell. No ceilings had been originally shown on plans for the stairwell.
|
INSP-Sprinkler Rough-in | 11/30/2006 | 12/1/2006 | 12/1/2006 | P | PART |
Forrest France
|
|
|
Inspection for cover at the drop ceilings in the tanning booth rooms, mens locker and womens locker- one head in the laundry room is overspaced off an adjacent wall, one head in the mens locker west side is overspaced, painted heads in the womens locker room to be replaced as discussed, remainder of ceilings in these areas inspected today are okay for cover.
|
Plan assigned to (Bill) | 7/24/2006 | | 11/28/2006 | | PASS |
|
|
|
11/28/2006 13:02:22 MWT - activity updated through activity FIRA22 from case FIR06-00891.
|
INSP-Sprinkler Rough-in/Hydro | 11/17/2006 | 11/17/2006 | 11/17/2006 | P | PASS |
Troy Cobbley
|
|
|
See city approved plans for hardlid areas marked with an "OK" that the sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 9/22/2006 | 9/25/2006 | 9/25/2006 | A | PART |
Forrest France
|
|
|
Sprinklers at the hard lid ceilings in the womens locker room as marked on approved plans are okay to cover.
|
INSP-Sprinkler Rough-in | 9/15/2006 | 9/18/2006 | 9/18/2006 | A | PASS |
Troy Cobbley
|
|
|
Hard lid areas in the northwest corner as marked on the plans are ok to cover
|
Issue and Print Permit | | | 8/22/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/21/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/21/2006 | | 8/21/2006 | | DONE |
|
|
|
|
Telephone call | | | 8/21/2006 | | DONE |
|
|
|
spoke to crystal@###-####/told permit was ready, permit#, project, and fee
|
Sprinkler Plan Check | | | 8/17/2006 | | PASS |
|
|
|
Reviewed by B. Johnson.
|
Miscellaneous action | | | 8/7/2006 | | DONE |
|
|
|
Early Start request approved for TVFP to begin system installation per submitted plans.
|
Application received | | | 7/24/2006 | | |
|
|
|
|