INSP-Final Inspection | 11/8/2006 | 11/9/2006 | 11/9/2006 | A | PASS |
Forrest France
|
|
|
Per final inspection completed by S. Arellano, fire sprinkler work is acceptable, permit finaled.
|
INSP-Sprinkler Rough-in | 8/29/2006 | 8/31/2006 | 8/31/2006 | A | PART |
Forrest France
|
|
|
OH sprinkler rough-in is good for cover at the hard lid areas.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/23/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/23/2006 | | 8/23/2006 | | DONE |
|
|
|
|
Telephone call | | | 8/23/2006 | | SPOK |
|
|
|
spoke to jon@###-####/told permit was ready, project name & address, and fee
|
Issue and Print Permit | | | 8/23/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 8/21/2006 | | PASS |
|
|
|
Resubmittal reviewed and approved by B. Johnson.
|
Plan resubmittals received | | | 8/17/2006 | | |
|
|
|
8/21 - Plans given to BJ for review.
|
Sprinkler Plan Check | | | 8/15/2006 | | FAIL |
|
|
|
Plans reviewed by B. Johnson. B. J. discussed review comments with contractor; faxed copy of review.
|
Plan assigned to (SAM) | 8/14/2006 | | 8/14/2006 | | DONE |
|
|
|
Plans sent to outside contractor for review to be done early this week.
|
Miscellaneous action | | | 8/14/2006 | | DONE |
|
|
|
Approved Early Start request from TVFP; scope of work limited to "rough-in sprinkler mains, lines and riser" prior to issuance of the permit and approved plans.
|
Application received | | | 7/27/2006 | | |
|
|
|
|