INSP-Final Inspection | 11/20/2007 | 11/20/2007 | 11/20/2007 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 11/6/2007 | 11/7/2007 | 11/8/2007 | A | PART |
Forrest France
|
|
|
Final pending ceiling tile and escutcheons, noted items from the previous inspection are complete.
|
INSP-Sprinkler Rough-in | 10/16/2007 | 10/17/2007 | 10/17/2007 | A | PART |
Troy Cobbley
|
|
|
This roughin was already done on Tuesday 10-16 under the wrong WPS. The ceiling tile is ok to install. Two rows of pendant sprinklers are blocked by duct work mounted at the ceiling level. The pendants have been installed outside of their listing. No other items except these heads were looked at. I spoke with the building representatives of WPS and we discussed height controls for the racks and moving the existing emergency lights which are at the deck to be below the new ceiling. I advised Forrest of the status.
|
Issue and Print Permit | | | 10/16/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/9/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/9/2007 | | 10/9/2007 | | DONE |
|
|
|
|
Telephone call | | | 10/9/2007 | | DONE |
|
|
|
tlk to lilly ###-####6 that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/9/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/24/2007 | | 10/8/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Plan resubmittals received | | | 9/24/2007 | | |
|
|
|
received fire apr app & "5" booklets including plans with each sheet of FP 1 of 3, 2 of 3 & 3 of 3 //plans put on shelf for fire
|
Plan resubmittals received | | | 8/22/2007 | | |
|
|
|
|
INSP-Conference | 7/16/2007 | 7/17/2007 | 7/17/2007 | A | DONE |
Forrest France
|
|
|
On site visit, discussed with contractor the requirement for the installation to comply with NFPA 13 2002, specifically 12.1.5 (1) regarding sprinkler protection per design for the more demanding area shall extend a min. of 15 ft. beyond its perimeter.
|
FIR-Aging Inspection | 3/8/2007 | 3/8/2007 | 3/12/2007 | | DONE |
Forrest France
|
|
|
Phone call to contractor to determine status, work in progress.
|
Sprinkler Plan Check | | | 11/7/2006 | | FAIL |
|
|
|
Plan modification to eliminate the dropped ceiling and protection extending 15' beyond the proposed racks which was show on the original plans reviewed by S.A. This Plan Modification review done by B. Johnson; review comments faxed by B.J. to Shilo and discussed with R. Knutson.
|
Plan resubmittals received | | | 10/20/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/14/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/11/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/11/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/11/2006 | | 8/11/2006 | | DONE |
|
|
|
|
Telephone call | | | 8/11/2006 | | DONE |
|
|
|
spoke to lilly@###-####/told permit was ready, permit#, project name & address, and fee
|
Application received | | | 8/10/2006 | | |
|
|
|
|
Plan assigned to (Scott) | 8/10/2006 | | 8/10/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/10/2006 | | 8/10/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Telephone call | | | 8/10/2006 | | DONE |
|
|
|
Requested 3rd copy of fire sprinkler plans from Randy Knutson of Shiloh Fire Protection.
|
Pending Assignment by SAM | 8/22/2007 | | | | |
|
|
|
|