INSP-Final Inspection | 4/27/2007 | 4/27/2007 | 4/27/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 4/26/2007 | 4/26/2007 | 4/27/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 4/13/2007 | 4/13/2007 | 4/13/2007 | P | FAIL |
Troy Cobbley
|
|
|
Above ground hydro test failed
|
INSP-Conference | 4/2/2007 | 4/3/2007 | 4/3/2007 | A | DONE |
Troy Cobbley
|
|
|
I went over life safety items with the contractor
|
INSP-Conference | 3/29/2007 | 3/30/2007 | 3/30/2007 | A | DONE |
Forrest France
|
|
|
Regarding questions for project life safety requirements.
|
Plan resubmittals received | | | 2/21/2007 | | |
|
|
|
|
INSP-Conference | 2/16/2007 | 2/20/2007 | 2/20/2007 | P | DONE |
Troy Cobbley
|
|
|
The roofing on the west end canopy is going to be permanently removed as well as the fire sprinkler protection.
|
INSP-Supply line flush | 2/2/2007 | 2/5/2007 | 2/5/2007 | A | PART |
Troy Cobbley
|
|
|
Underground flush passed. Overhead rough-in passed except for the 1 1/4" line to be run under the mezzanine. Fire pump has not been installed yet. Plans need to be resubmitted due to additional heads in the east end lower level calc area.
|
INSP-Supply line flush | 2/1/2007 | 2/2/2007 | 2/5/2007 | P | CANC |
Troy Cobbley
|
|
|
No time for inspection
|
INSP-Sprinkler Rough-in/Hydro | 2/1/2007 | 2/1/2007 | 2/1/2007 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro passed.
|
INSP-Supply line flush | 2/1/2007 | 2/1/2007 | 2/1/2007 | P | CANC |
Troy Cobbley
|
|
|
Inspection was ment to be called if for friday, not today.
|
INSP-Sprinkler Rough-in/Hydro | 1/29/2007 | 1/30/2007 | 1/30/2007 | A | PART |
Troy Cobbley
|
|
|
Hydro test was not ready. Rooms with ceilings are ok to cover
|
INSP-Sprinkler Rough-in | 8/25/2006 | 8/28/2006 | 8/28/2006 | | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover
|
Override - Parcel Holds | | | 8/25/2006 | | |
|
|
|
|
Plan assigned to (Bill) | 8/11/2006 | | 8/23/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/11/2006 | | 8/23/2006 | | PASS |
Troy Cobbley
|
|
|
Approved as noted with no written comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 8/23/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 8/23/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 8/23/2006 | | |
|
|
|
|
Inspection Record Card- Fire | 8/23/2006 | | 8/23/2006 | | DONE |
|
|
|
|
Telephone call | | | 8/23/2006 | | DONE |
|
|
|
spoke to lilly###-####/told permit was ready, permit#, project name & address, and fee
|
Override - Parcel Holds | | | 8/23/2006 | | |
|
|
|
|
Issue and Print Permit | | | 8/23/2006 | | |
|
|
|
|
Case Summary | | | 8/11/2006 | | DONE |
|
|
|
|
Application received | | | 8/11/2006 | | |
|
|
|
|