INSP-Final Inspection | 2/6/2007 | 2/6/2007 | 2/6/2007 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 2/2/2007 | 2/5/2007 | 2/5/2007 | P | CANC |
Troy Cobbley
|
|
|
Could not get access to the project due to an accident.
|
INSP-Final Inspection | 1/29/2007 | 1/30/2007 | 1/30/2007 | P | FAIL |
Troy Cobbley
|
|
|
No actual inspection was performed. I went through notification devices. Some need to be at a higher candella. The NAC panel has been relocated to the second floor. The smoke detector at this NAC needs relocated to the roof deck. As builts are required at the time of the next inspection. There appears to be a access controlled egress system at the doors which will need to be addressed.
|
INSP-Final Inspection | 1/26/2007 | 1/29/2007 | 1/29/2007 | P | CANC |
Troy Cobbley
|
|
|
Rob''s Phone Phone #: ###-#### Inspection cancelled from web by: Terry Owsley
|
Issue and Print Permit | | | 12/11/2006 | | DONE |
|
|
|
|
Telephone call | | | 12/8/2006 | | DONE |
|
|
|
t/c w raff at Protex ###-#### - permit ready and fees given ($374.70)
|
Permit Ready to Issue | | | 12/8/2006 | | DONE |
|
|
|
|
Alarm Plan Check | 12/7/2006 | | 12/7/2006 | | PASS |
|
|
|
Fire Alarm Resubmittal Review #3, Plan Review #4
Reluctantly Issued. See Fire Alarm Review Comments in Documents
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/7/2006 | | |
|
|
|
Ready for Issue
|
Inspection Record Card- Fire | 12/7/2006 | | 12/7/2006 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 8/11/2006 | | 12/7/2006 | | PASS |
|
|
|
12/7/2006 14:31:49 MWT - activity updated through activity FIRA22 from case FIR06-00592.
|
Plan assigned to (Mike) | 10/3/2006 | | 12/7/2006 | | PASS |
|
|
|
12/7/2006 14:31:49 MWT - activity updated through activity FIRA22 from case FIR06-00592.
|
Plan resubmittals received | | | 11/29/2006 | | |
|
|
|
|
Alarm Plan Check | 11/13/2006 | | 11/13/2006 | | FAIL |
|
|
|
Resubmittal Review #2
|
Telephone call | | | 11/13/2006 | | |
|
|
|
Faxed copy of 3rd review to Rob Ahten at Protex and Copie to Enterprise Electric.
|
Telephone call | | | 11/13/2006 | | DONE |
|
|
|
11-13-06 t/c w Rob Ahten at Protex ###-#### - informed him that a resubmittal was required on this application and was ready for pickup //ps
|
Plan resubmittals received | | | 11/2/2006 | | |
|
|
|
|
Telephone call | | | 10/3/2006 | | |
|
|
|
Faxed Copy of Fire Alarm System Review to Rob Ahten Protex
|
Miscellaneous action | | | 10/3/2006 | | |
|
|
|
Plans Taken to Front Desk for Resubmittal
|
Telephone call | | | 10/3/2006 | | DONE |
|
|
|
lft vm ###-#### that permit has failed needs to be resubmittal
|
Plan resubmittals received | | | 9/26/2006 | | |
|
|
|
Received new set of plans taken to Fire ///DLD
|
Alarm Plan Check | | | 8/24/2006 | | FAIL |
|
|
|
Plans are incomplete. Discussed with Rob Ahten; faxed review comments to Protex.
|
Application received | | | 8/11/2006 | | |
|
|
|
|
Case Summary | | | 8/11/2006 | | DONE |
|
|
|
|
Alarm Plan Check | 10/3/2006 | | | | FAIL |
|
|
|
Re-Submittal Review #1
|