INSP-Final Inspection | 11/25/2008 | 11/25/2008 | 11/25/2008 | A | PASS |
Forrest France
|
|
|
Fire alarm permit finaled.
|
Agreement of Future work | 4/18/2006 | 3/31/2011 | 11/25/2008 | | DONE |
Tim Frost
|
|
|
Phase 3 Upgrade Agreement
|
Agreement of Future work | 4/18/2006 | 10/31/2009 | 11/25/2008 | | DONE |
Tim Frost
|
|
|
Phase 2 Upgrade Agreement
|
Agreement of Future work | 4/18/2006 | 3/31/2008 | 11/25/2008 | | DONE |
Tim Frost
|
|
|
Phase 1 of Agreement
|
INSP-Final Inspection | 11/3/2008 | 11/3/2008 | 11/3/2008 | P | PART |
Forrest France
|
|
|
C/N items finished, record of completion forms to be submitted as discussed.
|
INSP-Final Inspection | 10/29/2008 | 10/29/2008 | 10/29/2008 | A | NR |
Forrest France
|
|
|
Pending record of completion forms.
|
INSP-Final Inspection | 10/27/2008 | 10/27/2008 | 10/27/2008 | P | PART |
Forrest France
|
|
|
Fire hat functionality both intermitent and solid tested satisfactory for all four elevators, final pending reciept of NFPA record of completion documents.
|
INSP-Final Inspection | 7/21/2008 | 7/22/2008 | 7/22/2008 | A | PART |
Forrest France
|
|
|
Final pending fire hat at elevators, per contractor the supervisory tamper switch at the 5th floor NE riser has been repaired and correctly programed-will verify at final inspection in conjunction with elevator controls as discussed.
|
INSP-Final Inspection | 7/3/2008 | 7/7/2008 | 7/7/2008 | A | FAIL |
Forrest France
|
|
|
Reviewed and reinspected defficient items noted at the previous inspection including elevator shunt trip power supervision, recall for car #3, new FJ at the pump room, new antifreeze system tamper, flow switch at the NE 2nd floor stairway, tampers at riser and floor control valves. Two remaining items in need of repair include the 5th floor NE tamper at the OS&Y sprinkler control valve, and provision for a flashing fire hat at the elevator cars upon FA device activation in the hoistway or machine room.
|
INSP-Final Inspection | 6/3/2008 | 6/5/2008 | 6/5/2008 | P | PART |
Forrest France
|
|
|
See list of correction notice items reviewed with contractor on site.
|
INSP-Conference | 6/3/2008 | 6/5/2008 | 6/5/2008 | P | DONE |
Forrest France
|
|
|
jose Phone #: ###-#### Regarding balance of inspection work for permit final.
|
INSP-Alarm Testing | 5/15/2008 | 5/15/2008 | 5/15/2008 | A | PART |
Forrest France
|
|
|
Per contractor approved plan set indicates removal of existing spot type smoke detectors at the mechanical penthouse area-if installed spacing must meet code requirements, discussed schedule for next site visit 5/20.
|
INSP-Final Inspection | 5/6/2008 | 5/6/2008 | 5/7/2008 | P | FAIL |
Forrest France
|
|
|
Inspection for elevator recall including testing lobby smoke detectors at all levels and elevator hoistway/ machine room devices. Noted shunt trip power supervision circut 20 address 122 did not report, SD 2031 is incorrectly located on the map (needs to be shown in the elevator machine room), the southeast car (elevator #3) is out of service-will need to verifiy recall at next visit, per ANSI/ASME A17.1-2000 Safety Code for Elevators- fire alarm initiating device activation in a machine room or hoistway shall cause the fire hat visual signal within the car to illuminate intermittently (2.27.3.2.6), noted SD locations at each of the four hoistways does not appear to meet requirements. Also noted spot type smoke detectors at the mechanical penthouse are not in compliance with NFPA 72 2002 sec. 5.7.3.2.1 and 5.7.3.2.4(B)(2) regarding mounting locations, beam obstructions and spacing 5.7.3.2.3 (A).
|
INSP-Final Inspection | 5/5/2008 | 5/5/2008 | 5/6/2008 | A | DEFR |
Forrest France
|
|
|
See inspection comments dated 5/6.
|
INSP-Final Inspection | 5/1/2008 | 5/2/2008 | 5/2/2008 | A | DEFR |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 5/1/2008 at 5:20:41 PM. Contact: ###-####.
|
INSP-Final Inspection | 4/23/2008 | 4/23/2008 | 4/23/2008 | P | NR |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 4/23/2008 at 8:03:15 AM. Contact: ###-####.
|
INSP-Alarm Testing | 4/23/2008 | 4/23/2008 | 4/23/2008 | A | CANC |
Forrest France
|
|
|
Duplicate inspection request.
|
INSP-Final Inspection | 4/21/2008 | 4/22/2008 | 4/23/2008 | A | PART |
Forrest France
|
|
|
Fire phones at all locations tested satisfactory, need to add one phone jack at the fire pump room. Also noted missing work table and land line phone at the fire command center to be provided as discussed.
|
INSP-Final Inspection | 3/31/2008 | 3/31/2008 | 3/31/2008 | P | CANC |
Forrest France
|
|
|
Wes ###-#### cancelled today by wes
|
INSP-Final Inspection | 3/27/2008 | 3/27/2008 | 3/27/2008 | P | NR |
Forrest France
|
|
|
Inspection to be rescheduled.
|
INSP-Alarm Testing | 3/13/2008 | 3/14/2008 | 3/14/2008 | A | PART |
Forrest France
|
|
|
Site inspection completed with respect to atrium beam detectors and smoke evacuation. Functional testing is satisfactory, approval pending verification of design data in correlation to actual test results.
|
INSP-Alarm Testing | 1/8/2008 | 1/9/2008 | 1/9/2008 | A | PART |
Forrest France
|
|
|
Fire alarm testing for the 3rd floor SW quad passed.
|
INSP-Alarm Testing | 12/10/2007 | 12/11/2007 | 12/11/2007 | A | PART |
Forrest France
|
|
|
Fire alarm testing for the 3rd floor NW quad area passed, noted correction items are complete.
|
INSP-Alarm Testing | 12/5/2007 | 12/7/2007 | 12/7/2007 | A | FAIL |
Forrest France
|
|
|
Fire alarm inspection for the 3rd floor NW quad failed due to missing av notification devices at three locations including a conference room, file room and open area.
|
INSP-Alarm Testing | 11/7/2007 | 11/8/2007 | 11/8/2007 | A | PART |
Forrest France
|
|
|
FA testing for the 3rd floor NE quad passed per K. Roule.
|
INSP-Alarm Testing | 11/5/2007 | 11/7/2007 | 11/7/2007 | A | FAIL |
Forrest France
|
|
|
FA inspection for the 3rd floor NE quad failed due to strobe synchronization issues.
|
INSP-Alarm Testing | 10/19/2007 | 10/22/2007 | 10/22/2007 | A | PART |
Forrest France
|
|
|
3rd floor SE quad fire alarm system modifications passed field testing.
|
INSP-Alarm Testing | 10/17/2007 | 10/19/2007 | 10/19/2007 | A | CANC |
Forrest France
|
|
|
Overbooked
|
CHANGE STATUS TO (ISS) | | | 10/17/2007 | | DONE |
|
|
|
plans picked up but erer not put back to issue mode 8-1-07 changed to issue 10-17-07 ///DLD
|
Inspection Record Card- Fire | 8/2/2007 | | 8/2/2007 | | DONE |
|
|
|
|
Telephone call | | | 8/2/2007 | | DONE |
|
|
|
t/c w rosanna at romar electric - ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/2/2007 | | DONE |
|
|
|
|
Alarm Plan Check | 7/31/2007 | | 8/1/2007 | | PASS |
|
|
|
Fire Alarm Review 5th - Plan Modification 3rd Floor
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2007 | | |
|
|
|
Ready for Issue Plan Modification 3rd Floor
|
Plan resubmittals received | | | 7/30/2007 | | |
|
|
|
|
Meeting | | | 6/11/2007 | | |
|
|
|
See attachment under documents 6-11-2007
|
INSP-Alarm Testing | 5/10/2007 | 5/11/2007 | 5/14/2007 | P | PART |
Forrest France
|
|
|
Fire alarm testing for the 1st floor SE quad as annotated on approved plans is satisfactory.
|
INSP-Alarm Testing | 5/9/2007 | 5/10/2007 | 5/10/2007 | A | CANC |
Forrest France
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Inspection | 4/28/2007 | 4/28/2007 | 4/28/2007 | | FAIL |
|
|
|
Fire alarm system testing; Saturday April 28, 2007 -Fail
1. HVAC Fan control from Fire Command Center tested Start/Stop - Pass
2. Stairway pressurization control from FCC tested Start/Stop - Pass
3. Plaza level North & South automatic door opening tested for smoke control - Pass
4. HVAC system status indicators are switch position indication only and are not true air flow or motor running status. Must be determined by Dave Hannemen.
5. Tested duct smoke detectors and AHU shutdown of basement air handlers AHU11, AHU9, AHU12, AHU13, AHU10 and AHU15. All duct detectors shut down units OK. However they are located in the supply air ductwork. Per the upgrade agreement and IFC 907.2.12.1 Duct detectors shall be located in the return air ducts. - Fail
6. Descriptor for basement FACP room smoke detector needs to be corrected. - Fail
7. FACP panel smoke detector to close to the diffuser must be relocated - Fail
8. Remove old non working fire alarm devices - Recheck as project progresses
9. Fire phone system not operational - To be tested as project progresses
10. Elevator annunciator panel does not indicate elevator floor locations - Install correct annunciator
11. Guard station annunciator not operational, paging system in place - Needs to be demonstrated.
12. One atrium exhaust fan wired incorrectly for remote operation - Corrected in place OK
13. Building dampers that isolate building penthouse HVAC control systems from the atrium smoke control removal did not operate. The control relays energized but dampers could not be shown that they would be overridden in an automatic smoke control sequence - Fail
14. Sprinkler system Flows & Tampers not tested. Need to be demonstrated
15. Several covers not installed on the new fire alarm control relays penthouse - To be corrected
16. Note: Cannot sign off Fire Permit Fir06-00595 until all floor level core areas are complete basement through penthouse see approved plans.
|
INSP-Alarm Testing | 4/27/2007 | 4/27/2007 | 4/27/2007 | P | PART |
Forrest France
|
|
|
See comments per field inspection by M. Timmerman scheduled for 4/28.
|
INSP-Alarm Testing | 4/23/2007 | 4/25/2007 | 4/26/2007 | P | DEFR |
Forrest France
|
|
|
See comments per field inspection by M. Timmerman.
|
INSP-Alarm Testing | 4/12/2007 | 4/13/2007 | 4/13/2007 | A | PART |
Forrest France
|
|
|
Testing for the basement manual pulls at the stairway exits, SD at the service elevator, SD for stairway pressure, and plaza level manual pulls at ground level stairway exits.
|
INSP-Alarm Testing | 3/23/2007 | 3/27/2007 | 3/27/2007 | P | CANC |
Forrest France
|
|
|
Pending correction of programing issues for descriptors and device address numbers matching an approved plan set.
|
INSP-Alarm Testing | 3/23/2007 | 3/26/2007 | 3/27/2007 | P | DEFR |
Forrest France
|
|
|
See notes per field inspection completed by M. Timmerman.
|
Case Summary | | | 3/27/2007 | | |
|
|
|
|
INSP-Final Inspection | 3/12/2007 | 3/13/2007 | 3/13/2007 | A | FAIL |
Forrest France
|
|
|
Re-inspection for the 4th floor corrections failed due to non-functional SD in the telephone and electrical rooms, and inadequate audibility for the SS notification devices.
|
INSP-Alarm Testing | 3/7/2007 | 3/9/2007 | 3/12/2007 | A | FAIL |
Forrest France
|
|
|
Inspection for the 5th floor Office supply tenant alarm work failed due to non-functional speakers at several locations, two SD have incorrect descriptors, as-built plans should reflect field changes, the notification and initiation devices at the north hall are not installed at this time. Also verified added SS at the mech. penthouse. Attempted test of the 1st floor atrium doors failed due to non-functional manual pull station at the reception desk.
|
INSP-Alarm Testing | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | PART |
Forrest France
|
|
|
Alarm testing for the 4th floor SE and SW quads only-retest of the av's passed but will need to add missing notification in conference room 4SE, manual pulls and SD at the SE tested okay , noted address # at the panel do not match two SD at the SW quad exit door and service elevator, also noted two non-functional SD in the SW telephone room and electrical room. Also tested av notification devices on the 2nd floor skybridges.
|
Plan resubmittals received | | | 2/28/2007 | | |
|
|
|
|
Plan resubmittals received | | | 2/14/2007 | | |
|
|
|
|
INSP-Alarm Testing | 1/24/2007 | 1/26/2007 | 1/26/2007 | A | FAIL |
Forrest France
|
|
|
Partial alarm notification testing completed for the 4th floor SE and SW quads and the entire penthouse. Noted two non-functional pull stations and one non-functional strobe at the 4th floor, still need to test the SD in the electrical and telephone rooms, the penthouse is missing one strobe to be added, one a/v is not functional on audio, only one manual pull tested at this time.
|
INSP-Sprinkler Rough-in | 1/17/2007 | 1/18/2007 | 1/18/2007 | A | PART |
Forrest France
|
|
|
Partial preliminary inspection for the CM's at the fire pump control valve tamper switches, noted two OS&Y valves out of adjustment, jockey pump, test header and system bypass tampers tested okay, remainder of pump supervision test pending. Also completed walk through and preliminary inspection of the penthouse/mechanical areas and the beam detectors at the atrium level.
|
INSP-Alarm Testing | 1/10/2007 | 1/11/2007 | 1/11/2007 | A | PART |
Forrest France
|
|
|
Inspection for the basement level audio/visual alarm notification functionality and coverage only completed today, noted file room coverage is lacking, still need to test manual pulls, relocated SD's, check EOL voltage.
|
INSP-Alarm Testing | 12/29/2006 | 1/2/2007 | 1/3/2007 | A | PART |
Forrest France
|
|
|
Inspection for location, spacing, cd rating, and installation of fire alarm notification devices at the basement level only. Noted on approved plans areas which are lacking proper coverage including the break room, mech. room, transformer room, and one hallway, also noted that FA wire must be attatched to the building structure per NFPA 72, no access was provided for the womens locker area or one server room at this inspection, will require as-built drawings at the next scheduled inspection reflecting changes made.
|
INSP-Alarm Testing | 12/6/2006 | 12/11/2006 | 12/11/2006 | A | PART |
Forrest France
|
|
|
2nd floor SW quad alarm test completed satisfactory.
|
INSP-Alarm Testing | 11/21/2006 | 11/22/2006 | 11/22/2006 | A | PART |
Forrest France
|
|
|
Re-inspection for the NW quad to verify required corrections completed satisfactory.
|
INSP-Alarm Testing | 11/17/2006 | 11/20/2006 | 11/20/2006 | A | DEFR |
Forrest France
|
|
|
don Note: if you cant do 6:30 we can do 5:00 pm; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Inspection to be rescheduled.
|
INSP-Alarm Testing | 11/13/2006 | 11/17/2006 | 11/17/2006 | A | FAIL |
Forrest France
|
|
|
Missing notification in the large confrence room at the NW quad, complete coverage is lacking in one portion of the common hallway, approved plans do not reflect actual field installation-will need as-builts showing modifications, the SW quad is not ready for final alarm inspection as field tile, lighting, finishes, etc. are not in place.
|
INSP-Conference | 10/20/2006 | 10/24/2006 | 10/24/2006 | A | DEFR |
Forrest France
|
|
|
Confrence to discuss location of beam detectors to be completed by M. Timmerman.
|
Miscellaneous action | | | 10/24/2006 | | |
|
|
|
Attended an inspection conference with Romar Electric, to discuss the location and mounting height of the Boise Cascade atrium smoke beam detectors. It was agreed that the contractor would locate the beam detectors as high as physically possible above the horizontal floor of the atrium. The new beam detectors will be spaced per the manufactures recommended spacing 30 - 60 feet. It was agreed that 30 foot spacing would be acceptable between the beam detectors and half of that distance would be allowed to a side wall of the atrium see manufacturers cut sheets.
|
INSP-Alarm Testing | 10/17/2006 | 10/20/2006 | 10/20/2006 | A | FAIL |
Forrest France
|
|
|
Testing for the 2nd floor NE quad only, need to relocate one notifcation device as marked on plans for proper coverage, missing one h/s at the west side division between quadrants, added sd at the electrical room to be shown on plans.
|
INSP-Alarm Testing | 10/13/2006 | 10/19/2006 | 10/19/2006 | A | DEFR |
Forrest France
|
|
|
Inspection to be performed on 10/20 per agreement.
|
INSP-Final Inspection | 10/6/2006 | 10/6/2006 | 10/6/2006 | P | FAIL |
Troy Cobbley
|
|
|
See Mike's inspection notes for items of this afternoons inspection
|
INSP-Sprinkler Rough-in | 10/5/2006 | 10/6/2006 | 10/6/2006 | A | FAIL |
Troy Cobbley
|
|
|
See Mike's inspection comments for correction items.
|
Alarm Plan Check | 10/4/2006 | | 10/5/2006 | | PASS |
|
|
|
4th Plan Review, 3rd Resubmittal
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/5/2006 | | |
|
|
|
Ready for Issue Permit Fee, 3rd Review and 4th Review fees should apply.
|
Inspection Record Card- Fire | 10/5/2006 | | 10/5/2006 | | DONE |
|
|
|
|
Telephone call | | | 10/5/2006 | | DONE |
|
|
|
tlk to sandy ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/5/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/5/2006 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 8/11/2006 | | 10/5/2006 | | PASS |
|
|
|
10/5/2006 13:14:08 MWT - activity updated through activity FIRA22 from case FIR06-00595.
|
Plan assigned to (Mike) | 9/18/2006 | | 10/5/2006 | | PASS |
|
|
|
10/5/2006 13:14:08 MWT - activity updated through activity FIRA22 from case FIR06-00595.
|
Plan resubmittals received | | | 10/3/2006 | | |
|
|
|
3rd Resubmittal Received
|
Telephone call | | | 9/29/2006 | | DONE |
|
|
|
Faxed 3rd Review Information to Wes Smith Romar Electric.
CC :David Burns Nelson Fire Systems in SLC
|
Telephone call | | | 9/29/2006 | | DONE |
|
|
|
sandy@###-####/told to call
|
Alarm Plan Check | 9/28/2006 | | 9/28/2006 | | FAIL |
|
|
|
Third Review Fire Alarm 9-28-06
|
Plan resubmittals received | | | 9/26/2006 | | |
|
|
|
Received plan re-submittals taken to Fire ( ok to take in per Mike T.)
|
Miscellaneous action | | | 9/21/2006 | | DONE |
|
|
|
Fax 2nd Review to Romar Wes Smith
|
Miscellaneous action | | | 9/21/2006 | | DONE |
|
|
|
Take 2nd Resubmittal To Front Desk for Return to Contractor
|
Telephone call | | | 9/21/2006 | | DONE |
|
|
|
spoke to sandy@###-####/told 2nd resubmittal was required
|
Miscellaneous action | | | 9/21/2006 | | DONE |
|
|
|
plans picked up by contractor
|
Alarm Plan Check | 9/19/2006 | | 9/21/2006 | | FAIL |
|
|
|
2nd Resubmittal Required
|
Alarm Plan Check | 9/6/2006 | | 9/21/2006 | | FAIL |
|
|
|
Re- Submittal Review Failed
|
Telephone call | | | 9/20/2006 | | DONE |
|
|
|
Called David Burns with Nelson Fire Alarm Systems (SLC Utah) asked David for UL listed spacing information on 177cd Speaker Strobes used on this project
|
Plan resubmittals received | | | 9/18/2006 | | |
|
|
|
|
Telephone call | | | 9/8/2006 | | DONE |
|
|
|
spoke to sandy@###-####/told resubmittal is required and that they can pick up this submittal
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/7/2006 | | FAIL |
|
|
|
Re-Submittal Required.
|
Miscellaneous action | | | 8/17/2006 | | DONE |
|
|
|
Early Start request from Romar Electric approved for scope of work to be: 1) rough-in of alarm system in 2nd floor office area, with no devices to be installed and 2) to install wiring and panels throughout the core of the building. Approved with condition: "The existing alarm system shall be maintained in service until the new alarm system is in service and has been inspected and approved."
|
Application received | | | 8/11/2006 | | |
|
|
|
|
INSP-Alarm Testing | 4/17/2007 | 4/18/2007 | | P | |
Forrest France
|
|
|
don - after 5p, said he talked to forrest; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
Inspection | 3/26/2007 | 3/26/2007 | | | FAIL |
|
|
|
After hours Inspection Boise Cascade Building. Fail
1.) The installing contractor is using a non- approved set of floor plans for installation of fire alarm equipment on the 4th floor. The approved set of plans was found in the general contractor's office, and after review the installation was significantly different than what was on the approved set of plans.
2.) Began by testing a smoke detector outside of the Northeast stairwell, found that an alarm verification feature is programmed into the automatic fire alarm detection devices. The main FACP descriptor associated with the smoke detector had only confusing identification numbers with no association to the floor or area of the detector location.
3.) Tested another smoke detector outside of freight elevator, alarm verification was enabled on this detector also. Finally after the detector went into alarm the smoke guard doors released and another confusing descriptor displayed at the main FACP. This time the descriptor said that the alarm was at the plaza level elevator smoke detector.
4.) It was decided that a meeting needs to be set up to discuss the procedure for installation, testing and correcting problems found during inspections. Also determine why installing workers are not working from approved plans.
|
Inspection | 10/6/2006 | 10/6/2006 | | | FAIL |
|
|
|
Fire Alarm System Only Inspection: South East Section of Boise Cascade Building 2nd Floor. Fail due to Smoke Detector for stairwell pressurization to close to HVAC Vent. Two office areas are being used as conference rooms visual notification is required room use not shown on plans.
|
Inspection | 10/6/2006 | 10/6/2006 | | | PASS |
|
|
|
Fire Alarm Inspection Only. 2nd Floor South East Quadrant Devices Added to Conference Rooms and HVAC Vent Moved Away From Smoke Detector. Alarm System Pass Only!! (Mike Timmerman)
|