INSP-Final Inspection | 2/9/2007 | 2/12/2007 | 2/13/2007 | A | PASS |
Troy Cobbley
|
|
|
Per Mike Timmerman this permit can be finaled.
|
Inspection | 2/13/2007 | 2/13/2007 | 2/13/2007 | | PASS |
|
|
|
Afternoon Inspection BODO 2/12/2007 Mike Timmerman
Inspected last two remaining items on the fire alarm system correction notice. 1. Interrupt Muzac system when fire alarm is in alarm. Tested Pass
2. Check accessible rooms for change out to 177cd visual notification devices. I was told that Forrest agreed if the devices were rotated to where they were not under the room ceiling they would be acceptable as is. Called and left message with Forrest to confirm. OK if this agreement was made.
|
INSP-Final Inspection | 2/9/2007 | 2/9/2007 | 2/9/2007 | P | CANC |
Troy Cobbley
|
|
|
Verify completion of c/n items Phone #: ###-#### Inspection cancelled from web by: Terry Owsley
|
INSP-Alarm Testing | 1/31/2007 | 2/1/2007 | 2/1/2007 | P | PART |
Forrest France
|
|
|
Need to retest elevator recall functions, the manual pull stations at the first floor lobby are installed above max. allowable height AFF, the tamper switch at the OS&Y @ tank suction is not functional, need to provide an additional module for the tank fill level monitoring, provide current as-builts and map at the panel, covers at SD shall be removed prior to final permit approval.
|
Plan resubmittals received | | | 1/29/2007 | | |
|
|
|
|
INSP-Alarm Testing | 1/18/2007 | 1/18/2007 | 1/18/2007 | P | PART |
Forrest France
|
|
|
Inspection for the 5th floor HD's, added SD in the meeting storage room, and testing for the common corridor detection devices completed today.
|
INSP-Alarm Testing | 1/16/2007 | 1/17/2007 | 1/17/2007 | A | PART |
Forrest France
|
|
|
Partial inspection for the 5th floor completed today including guest rooms, meeting rooms, laundry service and employee areas, and guest services. Need to provide an additional SD in the meeting storage room due to beam obstruction, testing of SD's in the common corridors pending clean hall conditions, heat detectors not tested at this time, programming issue at room 512 repaired while on site, elevator lobby and sprinkler floor controls remain to be tested, EOL, pulls, dampers, DH, and notification tested okay.
|
INSP-Final Inspection | 1/10/2007 | 1/16/2007 | 1/16/2007 | P | CANC |
Forrest France
|
|
|
No time to complete inspection due to high volume of scheduled requests.
|
INSP-Final Inspection | 1/10/2007 | 1/11/2007 | 1/10/2007 | P | CANC |
Forrest France
|
|
|
this is rafe''s cell. the inspection is for the 5th floor Phone #: ###-#### Inspection cancelled from web by: Terry Owsley
|
INSP-Final Inspection | 11/30/2006 | 12/1/2006 | 12/1/2006 | P | DEFR |
Forrest France
|
|
|
Per phone call from contractor, inspection rescheduled for 12/4.
|
Override - Parcel Holds | | | 11/30/2006 | | |
|
|
|
|
Override - Parcel Holds | | | 11/30/2006 | | |
|
|
|
|
INSP-Alarm Testing | 10/18/2006 | 10/20/2006 | 10/20/2006 | A | NR |
Forrest France
|
|
|
rob - note: fire alarm only - 6th floor ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith Sufficient visual notification coverage at ADA room 10x cannot yet be determined due to missing room finishes and hardware, door holders are not ready for inspection, elevator is not ready for inspection. Coverage at the SW ADA room and adjacent corridor is acceptable.
|
INSP-Final Inspection | 10/17/2006 | 10/19/2006 | 10/19/2006 | A | DEFR |
Forrest France
|
|
|
Per contractor, inspection to be rescheduled for 10/20 as discussed.
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 10/18/2006 | | |
|
|
|
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 10/17/2006 | | |
|
|
|
|
Override - Parcel Holds | | | 9/29/2006 | | |
|
|
|
|
Issue and Print Permit | | | 9/29/2006 | | |
|
|
|
|
Telephone call | | | 9/20/2006 | | DONE |
|
|
|
left mess that permit is ready
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/13/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/13/2006 | | 9/13/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/13/2006 | | DONE |
|
|
|
spoke rob@###-####/told permit was ready, project name,and fee
|
Alarm Plan Check | | | 9/12/2006 | | PASS |
|
|
|
Esubmittal reviewed and approved by M. Froemke, subject to attached comments.
|
Miscellaneous action | | | 9/7/2006 | | DONE |
|
|
|
Denied an emailed Early Start request to expand the scope of work to include installation of all devices, based on the breath of the 17 resubmittal items required per our review our 8/17/06 review including 12 areas where visual appliances were found to be inadequate (review comment #5).
|
Plan resubmittals received | | | 9/5/2006 | | |
|
|
|
|
Miscellaneous action | | | 8/17/2006 | | DONE |
|
|
|
Approved Early Start request from Tri State Electric for scope of work: to mount the FA panels and pull wire from each residence room back to the associated panels on floors 6 through 11.
|
Alarm Plan Check | | | 8/17/2006 | | FAIL |
|
|
|
Reviewed by M. Froemke. Review comments faxed to Protex 8/3/06.
|
Application received | | | 8/14/2006 | | |
|
|
|
|
Case Summary | | | 8/14/2006 | | DONE |
|
|
|
|
Plan assigned to (Mary) | 8/14/2006 | | | | |
|
|
|
|