INSP-Final Inspection | 1/12/2007 | 1/12/2007 | 1/12/2007 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Supply line flush | 11/29/2006 | 11/29/2006 | 11/29/2006 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed.
|
INSP-Sprinkler Rough-in | 10/11/2006 | 10/12/2006 | 10/12/2006 | P | PASS |
Troy Cobbley
|
|
|
Piping is ok to cover but depth of bury will have to be checked at final. Per Brian it will be ok due to landscaping. Top of pipe is 4'-9" below the building foundation and measures 14' off the face of the building. The 4'-6" will be verified.
|
Issue and Print Permit | | | 8/17/2006 | | DONE |
|
|
|
|
Plan assigned to (Scott) | 8/15/2006 | | 8/16/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/15/2006 | | 8/16/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/16/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/16/2006 | | 8/16/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/16/2006 | | DONE |
|
|
|
|
Telephone call | | | 8/16/2006 | | |
|
|
|
lft vm with jeff anderson ###-#### that permit and fees are ready to be picked up
|
Application received | | | 8/15/2006 | | |
|
|
|
|