INSP-Final Inspection | 11/9/2006 | 11/9/2006 | 11/9/2006 | P | PASS |
Forrest France
|
|
|
Correction items are complete, permit finaled.
|
INSP-Final Inspection | 11/8/2006 | 11/8/2006 | 11/8/2006 | P | FAIL |
Forrest France
|
|
|
Need to provide method for locking or sealing the control valves at the backflow in the open position, also need to provide signage at the control valves indicating thier function, see fire code review notes for requirements.
|
INSP-Sprinkler Rough-in | 8/30/2006 | 8/30/2006 | 8/30/2006 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover. Head has not been installed yet or the riser built.
|
Issue and Print Permit | | | 8/17/2006 | | DONE |
|
|
|
|
Application received | | | 8/16/2006 | | |
|
|
|
|
Sprinkler Plan Check | 8/16/2006 | | 8/16/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/16/2006 | | DONE |
|
|
|
|
Plan assigned to (Scott) | 8/16/2006 | | 8/16/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/16/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/16/2006 | | 8/16/2006 | | DONE |
|
|
|
|
Telephone call | | | 8/16/2006 | | DONE |
|
|
|
left vm for greg@###-####/told permit was ready, permit#, project name & address, and fee
|
Plan assigned to (Bill) | 8/16/2006 | | | | |
|
|
|
|