INSP-Final Inspection | 11/7/2007 | 11/7/2007 | 11/7/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 10/26/2006 | 10/27/2006 | 10/27/2006 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/29/2006 | 9/29/2006 | 9/29/2006 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Sprinkler Rough-in | 9/7/2006 | 9/8/2006 | 9/8/2006 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground supply piping is ok to cover.
|
INSP-Sprinkler Rough-in | 8/29/2006 | 8/29/2006 | 8/29/2006 | P | PART |
Troy Cobbley
|
|
|
Underground supply piping from the united water connection to the first 90 is ok to cover. The first 90 and the thrust block has not been installed yet.
|
Issue and Print Permit | | | 8/24/2006 | | DONE |
|
|
|
|
Telephone call | | | 8/21/2006 | | DONE |
|
|
|
spoke to sam@###-####/told permit was ready, permit#, project name & address, and fee
|
Plan assigned to (Scott) | 8/18/2006 | | 8/18/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/18/2006 | | 8/18/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/18/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 8/18/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/18/2006 | | 8/18/2006 | | DONE |
|
|
|
|
Case Summary | | | 8/17/2006 | | DONE |
|
|
|
|
Application received | | | 8/17/2006 | | |
|
|
|
|
Plan assigned to (Bill) | 8/17/2006 | | | | |
|
|
|
|