INSP-Final Inspection | 3/5/2007 | 3/6/2007 | 3/6/2007 | A | PASS |
Forrest France
|
|
|
Items on correction notice have been field verified for compliance, fire sprinkler final inspection passed.
|
INSP-Final Inspection | 2/28/2007 | 3/1/2007 | 3/1/2007 | P | DEFR |
Forrest France
|
|
|
No time available to complete inspection.
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2007 | 2/28/2007 | 2/28/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic test of the wet system passed, rough-in is okay, noted the need to install flex couplings at the mains on each side of the CMU wall where the pipe passes through and min. seismic clearance is not provided.
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2007 | 2/27/2007 | 2/27/2007 | P | NR |
Forrest France
|
|
|
Inspection rescheduled per phone call with contractor.
|
Plan assigned to (Bill) | 8/30/2006 | | 2/9/2007 | | PASS |
|
|
|
2/9/2007 13:31:50 MWT - activity updated through activity FIRA22 from case FIR07-00109.
|
INSP-Supply line flush | 1/23/2007 | 1/24/2007 | 1/24/2007 | A | CANC |
Forrest France
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2006 | 11/6/2006 | 11/6/2006 | P | DEFR |
Forrest France
|
|
|
Wrong permit number called in, was intended for the project related UG permitted work.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/19/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/19/2006 | | 9/19/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2006 | | DONE |
|
|
|
spoke to jeff@###-####/told permit was ready, project name, and fee
|
Issue and Print Permit | | | 9/19/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 9/15/2006 | | PASS |
|
|
|
Reviewed by B. Johnson.
|
Application received | | | 8/30/2006 | | |
|
|
|
|