INSP-Final Inspection | 1/24/2007 | 1/24/2007 | 1/24/2007 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Supply line flush | 1/23/2007 | 1/23/2007 | 1/23/2007 | P | FAIL |
Troy Cobbley
|
|
|
forward flush passed but the backflow still needs certified and the alarm interconnections tested.
|
INSP-Final Inspection | 1/18/2007 | 1/22/2007 | 1/22/2007 | A | FAIL |
Forrest France
|
|
|
The PIV tamper switch is not installed correctly, contractor to provide means for testing forward flow.
|
INSP-Sprinkler Rough-in/Hydro | 1/18/2007 | 1/22/2007 | 1/22/2007 | A | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test passed inspection.
|
INSP-Sprinkler Rough-in/Hydro | 1/17/2007 | 1/19/2007 | 1/17/2007 | A | CANC |
Forrest France
|
|
|
TYSON - UNDERGROUND INSPECTION; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
INSP-Final Inspection | 1/17/2007 | 1/19/2007 | 1/17/2007 | P | CANC |
Forrest France
|
|
|
TYSON - UNDERGROUND INSPECTION; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
INSP-Supply line flush | 1/4/2007 | 1/5/2007 | 1/5/2007 | A | PART |
Forrest France
|
|
|
UG supply line flush completed.
|
Plan assigned to (Bill) | 8/31/2006 | | 12/4/2006 | | PASS |
|
|
|
12/4/2006 12:59:27 MWT - activity updated through activity FIRA22 from case FIR06-00920.
|
INSP-Sprinkler Rough-in | 11/22/2006 | 11/22/2006 | 11/22/2006 | P | FAIL |
Forrest France
|
|
|
Need to provide some missing items at the riser including flexible couplings at the top and bottom, psi relief valve per review notes due to grid system, the automatic ball drip for the FDC needs to be relocated to the lowest point for proper operation. The overhead sprinkler rough-in installation is satisfactory.
|
INSP-Supply line flush | 10/16/2006 | 10/17/2006 | 10/17/2006 | A | PART |
Forrest France
|
|
|
UG fire supply line is acceptable for cover.
|
INSP-Sprinkler Rough-in | 10/16/2006 | 10/16/2006 | 10/16/2006 | P | FAIL |
Troy Cobbley
|
|
|
The bury depth still does not meet the minimum 4'-6" bury.
|
INSP-Sprinkler Rough-in/Hydro | 10/12/2006 | 10/13/2006 | 10/13/2006 | P | FAIL |
Forrest France
|
|
|
UG fire supply line does not meet requirements of NFPA 13 for the min. depth of bury. The pipe as installed is approx 10" to 12" too shallow.
|
Issue and Print Permit | | | 10/11/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/20/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/20/2006 | | 9/20/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/20/2006 | | DONE |
|
|
|
spoke to diane@###-####/told permit was ready, permit#, project name & address, and fee
|
Sprinkler Plan Check | | | 9/19/2006 | | PASS |
|
|
|
Plans reviewed by B. Johnson.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2006 | | DONE |
|
|
|
|
Case Summary | | | 8/31/2006 | | |
|
|
|
|
Application received | | | 8/31/2006 | | |
|
|
|
|