Permit Information
Permit NumberFIR06-00664
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 1444 S ENTERTAINMENT AVE
Project Name1444 S ENTERTAINMENT AVE
Customer Number 
ePlanReview 
Description
Anthem Office Building (Shell & Core) - To construct a new 77,000 square foot, five story, steel framed office building and related site improvements. This is a shell and core permit only and separate tenant improvement permits will be required to finish this building for occupancy. The core areas include stair enclosures, elevators and lobbies; restrooms at each floor; electrical room, hall, and janitors closet at each floor and fire riser room at the first floor. 1st fl: 16,180 sq. ft., 2nd fl: 15,280 sq. ft., 3rd fl: 15,260 sq. ft., 4th fl: 15,190 sq. ft., 5th fl: 15,190 sq. ft. This building is fully fire sprinklered. The sprinklers are used for height and story increase.
The scope of the sprinkler work includes running 270' of 6" C900 UG piping from the existing 12" water main located at West end of the property as drawn on sheet FP-1. From there stub up into the riser room. A combination standpipe will serve through out the 5 story bldg. The combination 4" standpipe will also supply a class I standpipe serving each floor and the roof. This design is of shell protection only. All sprinkler and standpipe work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This fire permit is attached to building permit: BLD06-01621. This is a shell and core permit only. Separate tenant improvement permits are required to finish this building for occupancy.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/24/20077/26/20077/26/2007APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection7/24/20077/25/20077/25/2007AFAIL
DetailsTroy Cobbley
Need forward flush, need sprinkler head in the elevator shaft relocted. The piping in the elevator shaft needs to be relocated due to the elevator guard rail. Signage is needed at the control vavles for the standpipes and at the fdc connection as discussed.
CHANGE STATUS TO (ISS)  7/24/2007 DONE
(F) Reprint permit  6/26/2007 DONE
(F) Reprint permit  6/26/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/25/2007 DONE
Inspection Record Card- Fire6/25/2007 6/25/2007 DONE
Telephone call  6/25/2007  
spoke to liz@###-####/told permit was ready, project name, and fee
Permit Ready to Issue  6/25/2007 DONE
Sprinkler Plan Check6/15/2007 6/22/2007 PASS
As-Built Plans are approved by Bryan Johnson
Plan resubmittals received  6/15/2007  
Received application, and five copies of wet system hydraulic calculation and drawings on pages F1, F2, F3, F4, F5, F6, F7, F8; taken to fire review
INSP-Sprinkler Rough-in/Hydro6/14/20076/14/20076/14/2007PPASS
DetailsTroy Cobbley
All above ground hydro tests passed except for the second floor and the fdc. The roof manifold was also flowed. The fire truck put out a max of 161psi which gave us 29 psi at the roof and 904gpm at the outlet. 141psi at the truck gave 100psi at the roof.
INSP-Sprinkler Rough-in5/29/20075/29/20075/29/2007PPASS
DetailsTroy Cobbley
The sprinkler piping located above the restrooms on the 1st, 2nd, 3rd, 4th and 5th floors is ok to cover
INSP-Supply line flush5/24/20075/25/20075/25/2007PNR
DetailsForrest France
Work not yet complete for inspection.
INSP-Sprinkler Rough-in5/8/20075/10/20075/11/2007PPART
DetailsTroy Cobbley
Today 5/10 I spent time on the Anthem project FIR06-00664, 1st - 4th floor.
The first floor standpipe connection was incomplete, otherwise the 1st floor was good.
The second floor was good with exception to a couple of under-spaced heads.
The third floor was done with exception to the aux drain a two missing heads that were shown but not installed.
The fourth floor was a little over done with 60 + extra 1.25" 90's added to the grid. I called for a re-sub for the calcs and drawings.
I also took a look at the 2nd floor TI upon request. FIR07-00103. It was in great shape.
INSP-Sprinkler Rough-in/Hydro4/19/20074/20/20074/20/2007PPASS
DetailsTroy Cobbley
underground hydro test passed
INSP-Sprinkler Rough-in/Hydro12/7/200612/8/200612/8/2006APASS
DetailsTroy Cobbley
The remaining section of underground supply line is ok to cover
INSP-Sprinkler Rough-in/Hydro12/7/200612/7/200612/7/2006PFAIL
DetailsTroy Cobbley
There is a hole in the ground but no piping installed. No workers around and the contact does not answer the phone
INSP-Sprinkler Rough-in11/2/200611/3/200611/3/2006APART
DetailsForrest France
The UG fire supply line stub out to approx. 8' and the riser stub are approved for cover.
PLANS/APPL TAKEN TO FRONT DESK  9/26/2006 DONE
Permit Ready to Issue  9/26/2006 DONE
Inspection Record Card- Fire9/26/2006 9/26/2006 DONE
Telephone call  9/26/2006 DONE
spoke to liz@###-####/told permit was ready, project name, and fee
Issue and Print Permit  9/26/2006 DONE
Sprinkler Plan Check  9/25/2006 PASS
Plans reviewed by B. Johnson.
Application received  9/5/2006  
Plan assigned to (Bill)9/5/2006