INSP-Final Inspection | 1/12/2007 | 1/16/2007 | 1/16/2007 | A | PASS |
Forrest France
|
|
|
Final fire sprinkler inspection passed, permit finaled.
|
INSP-Sprinkler Rough-in | 1/4/2007 | 1/5/2007 | 1/5/2007 | A | PART |
Forrest France
|
|
|
Sprinkler rough-in is now approved for cover at the kitchen drop ceiling area.
|
INSP-Sprinkler Rough-in/Hydro | 12/29/2006 | 1/2/2007 | 1/2/2007 | A | PART |
Forrest France
|
|
|
Hydrostatic test for the added piping passed, sprinkler installation is NOT approved for cover at the kitchen area due to obstructions to discharge created by insulation batting adjacent to the upright heads.
|
INSP-Sprinkler Rough-in | 11/28/2006 | 11/29/2006 | 11/29/2006 | A | PART |
Forrest France
|
|
|
OH rough-in is good for cover at the hard lid ceiling in the restroom only.
|
Plan assigned to (Bill) | 9/8/2006 | | 11/24/2006 | | PASS |
|
|
|
11/24/2006 15:37:17 MWT - activity updated through activity FIRA22 from case FIR06-00884.
|
INSP-Sprinkler Rough-in | 10/27/2006 | 10/30/2006 | 10/31/2006 | P | PART |
Forrest France
|
|
|
OH rough-in for cover is okay except as noted on approved plans, one ssu is missing abve the restroom, one head at a new entryway is not yet installed, annular space between the new wall and existing freezer wall may not be properly covered.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/26/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/26/2006 | | 9/26/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/26/2006 | | DONE |
|
|
|
spoke to brodie@###-####/told permit was ready, permit#, project name, and fee
|
Issue and Print Permit | | | 9/26/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 9/21/2006 | | PASS |
|
|
|
Reviewed by B. Johnson
|
Application received | | | 9/8/2006 | | |
|
|
|
|