INSP-Final Inspection | 11/16/2006 | 11/17/2006 | 11/17/2006 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 11/6/2006 | 11/9/2006 | 11/13/2006 | P | FAIL |
Troy Cobbley
|
|
|
Need ceiling tile installed prior to final.
|
INSP-Final Inspection | 10/30/2006 | 10/31/2006 | 10/31/2006 | A | PART |
Forrest France
|
|
|
Resubmitted plans verified on site to reflect the installation, rough-in is good for cover.
|
CHANGE STATUS TO (ISS) | | | 10/30/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/30/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/27/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/27/2006 | | 10/27/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/27/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 10/26/2006 | | PASS |
|
|
|
Re-submitted "as built" plans, reviewed by B. Johnson
|
Plan resubmittals received | | | 10/23/2006 | | DONE |
|
|
|
As built plans resubmitted for approval.
|
INSP-Sprinkler Rough-in | 10/16/2006 | 10/18/2006 | 10/18/2006 | P | FAIL |
Troy Cobbley
|
|
|
Plans do not match installation. Per Leroy the as-builts have been faxed downtown. I let him know that faxed as-builts won't be accepted. Especially faxed plans that have to be picked up downtown. The as-builts, had they been full size and on the job site would not have been accepted by me due to the amount of changes from the approved to the installed product. Leroy's shop drawings don't match either set. Resubmittals are going to be required.
|
Plan assigned to (Bill) | 9/11/2006 | | 10/16/2006 | | PASS |
|
|
|
10/16/2006 08:48:31 MWT - activity updated through activity FIRA22 from case FIR06-00785.
|
Issue permit | | | 10/4/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/2/2006 | | 10/2/2006 | | DONE |
|
|
|
|
Telephone call | | | 10/2/2006 | | DONE |
|
|
|
tlk to lily that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/2/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 9/25/2006 | | DONE |
|
|
|
Reviewed by B. Johnson
|
Application received | | | 9/11/2006 | | |
|
|
|
|