INSP-Final Inspection | 9/3/2007 | 9/4/2007 | 9/4/2007 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 7/25/2007 | 7/26/2007 | 7/26/2007 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given on the condition that the east elevator be locked out and not used until it has passed inspection. Also a plan holder is needed in the fire alarm panel control room to contain the building map.
|
INSP-Final Inspection | 7/24/2007 | 7/25/2007 | 7/25/2007 | A | FAIL |
Troy Cobbley
|
|
|
The elevator hat lights were not working in either elevator. The heat detector is too far away from the sprinkler head in the west elevator shaft and the a/v's on the first floor are missing their covers. The elevator testing needs to be started over.
|
INSP-Final Inspection | 7/23/2007 | 7/24/2007 | 7/24/2007 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for the items tested. Still need to perform elevator recall, provide covers and remove tape from a/v's, need as-built plans and map at facp, provide signage at the standpipe control vavles.
|
Plan assigned to (Mike) | 9/20/2006 | | 6/25/2007 | | PASS |
|
|
|
6/25/2007 15:17:00 CMC - activity updated through activity FIRA22 from case FIR06-00664.
|
FIR-Aging Inspection | 12/29/2006 | 12/29/2006 | 12/29/2006 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
Issue and Print Permit | | | 9/27/2006 | | DONE |
|
|
|
|
Alarm Plan Check | 9/26/2006 | | 9/26/2006 | | PASS |
|
|
|
Fire Alarm Review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 9/26/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/26/2006 | | DONE |
|
|
|
left vm for charlie@###-####/told permit was ready, project name, and no fee
|
Inspection Record Card- Fire | 9/26/2006 | | 9/26/2006 | | DONE |
|
|
|
|
Application received | | | 9/19/2006 | | |
|
|
|
|