INSP-Final Inspection | 5/27/2010 | 6/1/2010 | 6/1/2010 | A | PASS |
Troy Cobbley
|
|
|
Jeff and I met at the project and went over the drawings. It appears the 8' isles referenced was a typo since in the design curve "C" was used which covers multiple racks and 4' isles. Permit finaled.
|
Miscellaneous action | | | 3/11/2010 | | DONE |
|
|
|
Sent email requesting project status.
|
INSP-Final Inspection | 12/27/2006 | 12/28/2006 | 12/29/2006 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave hannimans permission until the sprinkler design/aisle widths are figured out.
|
INSP-Sprinkler Rough-in/Hydro | 12/27/2006 | 12/28/2006 | 12/28/2006 | A | FAIL |
Troy Cobbley
|
|
|
The rack system overhead hydro test failed. All other items have been corrected. Forward flush passed.
|
INSP-Final Inspection | 12/26/2006 | 12/27/2006 | 12/27/2006 | A | CANC |
Troy Cobbley
|
|
|
bryan ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
INSP-Sprinkler Rough-in/Hydro | 12/26/2006 | 12/27/2006 | 12/27/2006 | A | FAIL |
Troy Cobbley
|
|
|
Hydro test failed due to new heads needing added. Atleast one head is needed on the east side of the riser room and another to provide column protection per Chapter 12. Provide flexible couplings for the 4" riser piping at the racks. I notified the general contractor that there can be no storage below the stairs or sprinkler protection will be required. Also there are many screws for the rack piping hangers that are not ran all the way into the supporting structure.
|
INSP-Final Inspection | 12/22/2006 | 12/26/2006 | 12/26/2006 | A | NR |
Forrest France
|
|
|
Cancel per phone call from contractor, not ready for inspection due to a split pipe in need of repair.
|
INSP-Sprinkler Rough-in/Hydro | 12/22/2006 | 12/22/2006 | 12/22/2006 | P | FAIL |
Troy Cobbley
|
|
|
The above ground hydro test for both systems failed. But to Brians credit I was unable to make it back to the project in two hours.
|
Telephone call | | | 10/6/2006 | | |
|
|
|
tlk to jeff anderson ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/6/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/6/2006 | | 10/6/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/6/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 9/19/2006 | | 10/5/2006 | | PASS |
|
|
|
10/5/2006 16:01:44 MWT - activity updated through activity FIRA22 from case FIR06-00710.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/5/2006 | | |
|
|
|
Ready for Issue
|
Application received | | | 9/19/2006 | | |
|
|
|
|
Case Summary | | | 9/19/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/5/2006 | | | | PASS |
|
|
|
Fire Sprinkler Review done by Brian Johnson, Logged by MWT
|