INSP-Final Inspection | 2/12/2008 | 2/12/2008 | 2/12/2008 | P | PASS |
Forrest France
|
|
|
UG fire supply line permit finaled.
|
INSP-Sprinkler Rough-in | 1/14/2008 | 1/14/2008 | 1/14/2008 | P | CANC |
Forrest France
|
|
|
Wrong permit number called in for inspection.
|
INSP-Sprinkler Rough-in/Hydro | 12/5/2007 | 12/6/2007 | 12/6/2007 | A | PART |
Forrest France
|
|
|
OH is approved for cover at the drop ceilings on the 2nd, 3rd and 4th floor common corridors only, noted one missing drop and hanger restraint at the 3rd floor corridor-can be verifed at next inspeciton.
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2007 | 7/3/2007 | 7/3/2007 | A | PART |
Forrest France
|
|
|
OH hydrostatic testing for the attic dry system completed okay, remainder of the dry system rough-in failed due lacking coverage at the east side of the elevator shaft, two uprights at the west end are installed too low, one plugged outlet needs to be rotated to avoid water collection and freeze potential, items from previous inspection have been corrected.
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2007 | 6/27/2007 | 6/27/2007 | P | FAIL |
Forrest France
|
|
|
Partial inspection of the dry system for work completed to date as marked on plans, noted overspaced heads at some locations, heads at two areas exceed min.separation, several heads (approx. 35) have been added to cover overbuilds-need to resubmit plans reflecting changes as this work exceeds the scope allowed for field approval.
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2007 | 6/21/2007 | 6/21/2007 | A | PART |
Forrest France
|
|
|
Hydrostatic tests for the UG supply line, OH wet systems floors 1st, 2nd, 3rd passed inspection.
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2007 | 6/19/2007 | 6/20/2007 | P | PART |
Forrest France
|
|
|
OH rough-in is acceptable for the 1st and 2nd floor wet systems, noted field mods on the 1st floor, 2nd floor dead end 1" pipe in the wall to be removed and capped above the ceiling.
|
INSP-Supply line flush | 6/12/2007 | 6/13/2007 | 6/14/2007 | P | PART |
Forrest France
|
|
|
Completed UG fire supply line flush.
|
INSP-Sprinkler Rough-in/Hydro | 6/12/2007 | 6/13/2007 | 6/13/2007 | P | PART |
Forrest France
|
|
|
4th floor rough-in is acceptable, noted two locations in need of hanger restraints and one pipe in excess of allowed deflection.
|
INSP-Supply line flush | 10/2/2006 | 10/4/2006 | 10/4/2006 | A | PART |
Troy Cobbley
|
|
|
Inspection was for cover of the underground pipe. Piping is ok to cover from the building stub-in up to the last 45 elbow. The PIV and the connection to united water has not been completed yet.
|
Inspection Record Card- Fire | 10/2/2006 | | 10/2/2006 | | DONE |
|
|
|
|
Telephone call | | | 10/2/2006 | | DONE |
|
|
|
tlk to jack zastrow ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/2/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/2/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 9/22/2006 | | 9/29/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/29/2006 | | 9/29/2006 | | DONE |
|
|
|
No seperate plan review notes attached.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/29/2006 | | |
|
|
|
|
Application received | | | 9/22/2006 | | |
|
|
|
|