INSP-Final Inspection | 7/31/2007 | 8/1/2007 | 8/1/2007 | P | PASS |
Forrest France
|
|
|
Final shell fire sprinkler permit inspection passed, noted defficiencies corrected.
|
INSP-Final Inspection | 7/30/2007 | 7/31/2007 | 7/31/2007 | A | FAIL |
Forrest France
|
|
|
Overspaced heads at locations on the 2nd and 3rd floors as indicated on site.
|
INSP-Final Inspection | 7/27/2007 | 7/30/2007 | 7/30/2007 | A | DEFR |
Forrest France
|
|
|
To be completed in conjunction with the project related fire alarm permit final inspection.
|
INSP-Final Inspection | 7/25/2007 | 7/26/2007 | 7/26/2007 | A | FAIL |
Forrest France
|
|
|
Low air switch at the dry system riser is not set properly, air compressor must be hard wired without an off switch, lacking coverage at one storage room in the basement, provide 911 signage at the outside bell, covered heads and missing escutcheons at some locations, head in the riser room is covered with fireproofing, inspection concluded at this time due to number of defficiencies.
|
INSP-Sprinkler Rough-in | 6/20/2007 | 6/21/2007 | 6/21/2007 | A | CANC |
Forrest France
|
|
|
Wrong permit number called in for inspection.
|
INSP-Sprinkler Rough-in | 6/18/2007 | 6/19/2007 | 6/19/2007 | A | FAIL |
Forrest France
|
|
|
Wrong permit number called in for inspection, was intended for a project related tenant improvement under FIR07-00270. Inspection failed due to overspaced heads at five locations, two heads in a conference room are cut in a the wrong ceiling height, missing approved plans which are required to be on site as a condition of the permit, a hold currently exists on this permit due to overdue fees.
|
INSP-Final Inspection | 6/1/2007 | 6/7/2007 | 6/7/2007 | A | NR |
Forrest France
|
|
|
Per phone call from the contractor, project is not ready for final due to related alarm work issues.
|
INSP-Final Inspection | 5/9/2007 | 5/16/2007 | 5/14/2007 | A | CANC |
Forrest France
|
|
|
Mike Bierman is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2007 | 4/5/2007 | 4/5/2007 | A | DONE |
Forrest France
|
|
|
Air test concluded.
|
INSP-Supply line flush | 4/3/2007 | 4/4/2007 | 4/4/2007 | A | PART |
Forrest France
|
|
|
Air test restarted.
|
INSP-Sprinkler Rough-in | 3/21/2007 | 3/22/2007 | 3/23/2007 | A | FAIL |
Forrest France
|
|
|
Dry system air test failed due to 3 psi. loss at the guage.
|
INSP-Sprinkler Rough-in | 3/20/2007 | 3/21/2007 | 3/21/2007 | A | PART |
Troy Cobbley
|
|
|
This is a 24 hour air test. Test started at 11:00am with 40psi on the guage.
|
Issue and Print Permit | | | 2/27/2007 | | DONE |
|
|
|
|
Telephone call | | | 2/23/2007 | | DONE |
|
|
|
tlk to lily that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 2/23/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/21/2007 | | 2/22/2007 | | PASS |
|
|
|
Plans resubmittal 2 review by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/22/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/22/2007 | | 2/22/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/13/2007 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 1/31/2007 | 2/1/2007 | 2/1/2007 | A | FAIL |
Forrest France
|
|
|
Per field inspection completed by B. Johnson, upright heads at several locations are obstructed by ductwork.
|
INSP-Supply line flush | 1/26/2007 | 1/29/2007 | 1/29/2007 | P | PART |
Forrest France
|
|
|
UG supply line flush completed satisfactory, noted control valve manifold at the 2nd floor to be repiped for the provision of adequate and reasonable access.
|
INSP-Sprinkler Rough-in/Hydro | 12/6/2006 | 12/7/2006 | 12/7/2006 | A | PART |
Forrest France
|
|
|
UG hydrostatic test for the fire supply line completed satisfactory.
|
INSP-Sprinkler Rough-in | 11/16/2006 | 11/17/2006 | 11/17/2006 | A | PART |
Forrest France
|
|
|
UG fire supply line is acceptable for cover pending AG system design is compatible with the configuration of the underground supply piping.
|
Inspection Record Card- Fire | 11/15/2006 | | 11/15/2006 | | DONE |
|
|
|
|
Telephone call | | | 11/15/2006 | | DONE |
|
|
|
t/c w Randy Knutson at Shilo Automatic Sprinkler ###-#### - permit ready and no fee (plan modification - re-issued permit)
|
Permit Ready to Issue | | | 11/15/2006 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/15/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 11/15/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/14/2006 | | |
|
|
|
|
Sprinkler Plan Check | 11/14/2006 | | 11/14/2006 | | PASS |
|
|
|
Underground plan modification.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/14/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/8/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 9/22/2006 | | 11/7/2006 | | PASS |
|
|
|
11/7/2006 16:01:37 SLR - activity updated through activity FIRA22 from case FIR06-00728.
|
Sprinkler Plan Check | | | 11/7/2006 | | PASS |
|
|
|
Resubmittal reviewed by B. Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/7/2006 | | DONE |
|
|
|
|
Telephone call | | | 11/7/2006 | | DONE |
|
|
|
tlk to lily that permita and fees are ready to be picked up
|
Inspection Record Card- Fire | 11/7/2006 | | 11/7/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/7/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/24/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 10/16/2006 | | FAIL |
|
|
|
Reviewed by B. Johnson. Report indicates: "Contractor may proceed on the conditions that required changes/modifications meeting minimum code are provided and verified prior to completion/approval. No inspection shall be called prior to approved, stamped plans on site addressing any issues outlined below." Review comments faxed to contractor.
|
Application received | | | 9/22/2006 | | |
|
|
|
|