INSP-Final Inspection | 1/12/2007 | 1/12/2007 | 1/12/2007 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/10/2007 | 1/11/2007 | 1/11/2007 | P | CANC |
Troy Cobbley
|
|
|
Per discussion with Troy this inspection will be rescheduled with the alarms and life safety
|
INSP-Sprinkler Rough-in/Hydro | 1/10/2007 | 1/11/2007 | 1/11/2007 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test on the dry system and the forward flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 1/9/2007 | 1/10/2007 | 1/10/2007 | A | PART |
Troy Cobbley
|
|
|
Overhead hydro test passed for the wet system. 24 hour air test started on the dry system at 8:30 with 40 3/4psi on the guage.
|
INSP-Sprinkler Rough-in/Hydro | 12/15/2006 | 12/18/2006 | 12/18/2006 | A | PART |
Troy Cobbley
|
|
|
Wet system sprinkler piping is ok to cover except the three areas where the earthquaking still needs to be installed.
|
INSP-Sprinkler Rough-in/Hydro | 11/21/2006 | 11/21/2006 | 11/21/2006 | | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2006 | 10/13/2006 | 10/13/2006 | A | PASS |
Troy Cobbley
|
|
|
Dry system sprinkler piping ok to cover. I went over the requirement for resubmitting the fdc location with troy.
|
Telephone call | | | 10/11/2006 | | DONE |
|
|
|
tlk to jeff anderson ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/11/2006 | | |
|
|
|
|
Issue and Print Permit | | | 10/11/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/11/2006 | | 10/11/2006 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 9/25/2006 | | 10/10/2006 | | PASS |
|
|
|
10/10/2006 15:11:51 SLR - activity updated through activity FIRA22 from case FIR06-00733.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 10/7/2006 | | PASS |
|
|
|
Reviewed by B. Johnson.
|
Miscellaneous action | | | 10/6/2006 | | DONE |
|
|
|
Recieved another set of plans
|
Miscellaneous action | | | 10/5/2006 | | DONE |
|
|
|
Early start request by sprinkler contactor approved. Missing set of original plan submittals. Contractor contacted and will resubmit 3 sets to PDS for review.
|
Application received | | | 9/25/2006 | | |
|
|
|
|