INSP-Final Inspection | 12/14/2006 | 12/15/2006 | 12/15/2006 | A | PASS |
Forrest France
|
|
|
Required corrections are complete, fire alarm passed inspection.
|
INSP-Final Inspection | 12/13/2006 | 12/14/2006 | 12/14/2006 | P | FAIL |
Forrest France
|
|
|
Notification devices are overspaced or lacking at some areas as noted, need to program duct detection devices for HVAC shutdown, will need to test the remainder of work for the shell permit including the elevator controls prior to occupancy for this tenant.
|
Plan assigned to (Mike) | 9/27/2006 | | 10/9/2006 | | PASS |
|
|
|
10/9/2006 10:03:51 MWT - activity updated through activity FIRA22 from case FIR06-00746.
|
Alarm Plan Check | 10/9/2006 | | 10/9/2006 | | PASS |
|
|
|
New Application Received (Corrected)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/9/2006 | | |
|
|
|
Ready for Issue
|
Permit Ready to Issue | | | 10/9/2006 | | |
|
|
|
|
Telephone call | | | 10/9/2006 | | DONE |
|
|
|
lft vm with rob ahten ###-#### that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 10/9/2006 | | 10/9/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/9/2006 | | DONE |
|
|
|
|
Case Summary | | | 9/27/2006 | | DONE |
|
|
|
|
Application received | | | 9/27/2006 | | |
|
|
|
|
Alarm Plan Check | 10/3/2006 | | | | FAIL |
|
|
|
Begin Fire Alarm System Review
|