INSP-Final Inspection | 2/6/2007 | 2/6/2007 | 2/6/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 1/31/2007 | 1/31/2007 | 1/31/2007 | A | PART |
Forrest France
|
|
|
Need to properly install and adjust the tamper switch at the PIV. The remainder of fire alarm work tested satisfactory.
|
Issue and Print Permit | | | 10/5/2006 | | DONE |
|
|
|
|
Plan assigned to (Mike) | 9/28/2006 | | 10/4/2006 | | PASS |
|
|
|
10/4/2006 08:31:23 MWT - activity updated through activity FIRA22 from case FIR06-00749.
|
Alarm Plan Check | 10/4/2006 | | 10/4/2006 | | PASS |
|
|
|
Begin Fire Alarm System Review
|
Telephone call | | | 10/4/2006 | | |
|
|
|
Called protex office, left message for Rob that I need battery calculations for Fire Alarm Control Panel that were not submitted with plans.
|
Miscellaneous action | | | 10/4/2006 | | |
|
|
|
Found battery calculation sheet stuck to the back of matrix. Called Protex left message calculations found.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/4/2006 | | |
|
|
|
Ready for Issue
|
Inspection Record Card- Fire | 10/4/2006 | | 10/4/2006 | | DONE |
|
|
|
|
Telephone call | | | 10/4/2006 | | DONE |
|
|
|
lft vm with ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/4/2006 | | |
|
|
|
|
Case Summary | | | 9/28/2006 | | DONE |
|
|
|
|
Application received | | | 9/28/2006 | | |
|
|
|
|