INSP-Final Inspection | 7/9/2008 | 7/10/2008 | 7/10/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 5/7/2008 | 5/9/2008 | 5/9/2008 | A | PART |
Forrest France
|
|
|
Phone #: ###-#### Internet Inspection Request from: John Warnick
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2007 | 1/22/2007 | 1/22/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic test is satisfactory, noted one head in the riser room to be changed to an intermediate temp. due to high ambient heat conditions, as-built plans need to reflect deletion of the SW heads at garage doors no longer of the overhead type, need to complete forward flow prior to final approval.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2006 | | DONE |
|
|
|
|
Telephone call | | | 10/20/2006 | | DONE |
|
|
|
tlk with commercial fire ###-#### that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 10/20/2006 | | 10/20/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/20/2006 | | DONE |
|
|
|
|
Issue permit | | | 10/20/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 10/19/2006 | | PASS |
|
|
|
Reviewed by B. Johnson.
|
Application received | | | 10/10/2006 | | |
|
|
|
|
Pending Assignment by SAM | 10/10/2006 | | | | |
|
|
|
|