Miscellaneous action | | | 10/19/2007 | | DONE |
|
|
|
Sent an e-mail to Owner and Fire Alarm Vendor requesting the Submitted As-Built plans be corrected with a few devices that addresses are not shown Mike Timmerman 10-19-2007
|
INSP-Final Inspection | 10/1/2007 | 10/2/2007 | 10/2/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 9/28/2007 | 9/28/2007 | 10/1/2007 | P | FAIL |
Troy Cobbley
|
|
|
See Ken's field notes on the city approved plans for the items tested.
|
Alarm Plan Check | | | 9/28/2007 | | PASS |
|
|
|
Fire Alarm Review 3rd "Pass" with conditions on Review Notes.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/2007 | | |
|
|
|
Ready for Issue - Conditions, see review comments
|
Inspection Record Card- Fire | 9/28/2007 | | 9/28/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/28/2007 | | |
|
|
|
tlk to Roxanne ###-#### for Bob Beard that permit is ready to be picked up
|
Permit Ready to Issue | | | 9/28/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/28/2007 | | DONE |
|
|
|
|
Miscellaneous action | | | 9/25/2007 | | |
|
|
|
Called the electrical contractor Dick Mather ###-####. They would like to have an inspection today, however, the resubmitted plans have not been issued yet. This is keeping the alarm contractor from being able to call in their inspections. We will be going to the site to continue the alarm testing of system devices that are ready for inspection. The electrical contractor told me that the problem with the in room detector sounder bases is still causing problems. They are still working on the problem. Entry made by Mike Timmerman
|
Alarm Plan Check | | | 9/25/2007 | | FAIL |
|
|
|
Fire Alarm Review 3rd
|
Miscellaneous action | | | 9/25/2007 | | |
|
|
|
Fax copy of review to applicant John Thompson RFI
|
Inspection | | | 9/25/2007 | | PART |
|
|
|
See documents for correction Items to be made.
|
INSP-Alarm Testing | 9/24/2007 | 9/24/2007 | 9/24/2007 | P | FAIL |
Troy Cobbley
|
|
|
The fire alarm panel, after testing between two to six room detectors will automatically silence the sounder bases. I do not know if the panel silences all building alarms. Also the data from one of the tenant rooms is being corrupted by the time it is received at the facp and is causing "wave form" errors at the facp. I spoke to the Pyrotronics technical support and they believe that the silencing problem could be a logic/programming issue. They need to view the program to tell. I stopped the inspection out of concerns that if it is a hardware issue all of the items tested would have to be retested when a new panel is installed. Just to make a note when the main fire alarm panel is reset it takes nearly 7 minutes to return to normal. It also takes around 15 seconds to activate the sounder bases in the rooms. I was told this is due to the size of the system and a slow processor in the fire alarm panel. I spoke to Sam Rogers about these concerns. This entry has been made under this permit only due to none access to the other permits because of their being in the "review status"
|
Plan resubmittals received | | | 9/24/2007 | | |
|
|
|
Received three copies of 1pg. voltage drop calcs, 1pg. battery calcs, and check for $330.00 (put in safe); taken to Mike Timmerman
|
Plan assigned to (Mike) | 9/19/2007 | | 9/24/2007 | | PASS |
|
|
|
9/24/2007 10:08:00 CMC - activity updated through activity FIRA22 from case FIR06-00957.
|
INSP-Alarm Testing | 9/18/2007 | 9/21/2007 | 9/21/2007 | A | DONE |
Troy Cobbley
|
|
|
See the city approved plans for locations tested by Ken.
|
INSP-Alarm Testing | 9/18/2007 | 9/20/2007 | 9/20/2007 | A | CANC |
Troy Cobbley
|
|
|
Overbooked with Micron plan review.
|
INSP-Alarm Testing | 9/18/2007 | 9/19/2007 | 9/19/2007 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection was actually a conference with the fire alarm designer. Mike Timmerman and I went over the a/v and smoke detector deficiencies with him. Mike is allowing him to red line the resubmittals that are waiting in line at the city for review.
|
INSP-Alarm Testing | 9/17/2007 | 9/18/2007 | 9/18/2007 | A | DONE |
Troy Cobbley
|
|
|
No actual inspection was perform today do to multiple problems found.They include the fire alarm panel does not sound on second alarm. There are many over spaced detectors in lounge area. There are areas where smoke detectors and a/v's need to be added. In the dining areas the cieling mounts a/v'sare know mounted on the walls. The kithen area has same problems as well. The contractor needs to resubmit these changes.
|
INSP-Alarm Testing | 9/17/2007 | 9/17/2007 | 9/17/2007 | A | FAIL |
Troy Cobbley
|
|
|
The dialer was in trouble and would not clear. No test performed.
|
INSP-Alarm Testing | 9/13/2007 | 9/14/2007 | 9/14/2007 | A | DONE |
Troy Cobbley
|
|
|
See the city approved plans for devices tested in area D.
|
INSP-Alarm Testing | 9/13/2007 | 9/13/2007 | 9/13/2007 | A | CANC |
Troy Cobbley
|
|
|
Overbooked
|
Miscellaneous action | | | 9/5/2007 | | |
|
|
|
The fire alarm vendor brought in a new set of fire alarm plans with plan modifications for review due to the increase in number of fire smoke dampers, fire sprinkler devices, addition of manual pull boxes due to IDHW requirements not IFC. The plans were not acceptable new devices were not shown connected to the initiating circuits, Visual notification in the HC rooms was not shown, Plans now use areas A.B,C,D instead of east, west, south and central wing. This needs to be revised on the resubmitted plans. We have asked the alarm vendor to correct the mistakes and omissions on the fire alarm plans, before we take them in. 9-5-07
|
INSP-Final Inspection | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | CANC |
Troy Cobbley
|
|
|
No alarm inspection performed today. Just sprinklers were looked at.
|
CHANGE STATUS TO (ISS) | | | 1/19/2007 | | |
|
|
|
no fee due changed to issued status
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/10/2007 | | |
|
|
|
Ready for Issue
|
Inspection Record Card- Fire | 1/10/2007 | | 1/10/2007 | | DONE |
|
|
|
|
Telephone call | | | 1/10/2007 | | DONE |
|
|
|
t/c w roxanne at RFI -###-#### - permit ready and no fees
|
Permit Ready to Issue | | | 1/10/2007 | | DONE |
|
|
|
|
Plan assigned to (Mike) | 10/18/2006 | | 1/10/2007 | | PASS |
|
|
|
1/10/2007 12:21:58 MWT - activity updated through activity FIRA22 from case FIR06-00811.
|
Alarm Plan Check | 12/18/2006 | | 1/10/2007 | | PASS |
|
|
|
Waiting on generator Information, alarm vendor is using 4 hours of standby battery time and emergency generator backup. No Generator or fuel information was provided with the submittals.
Gernerator Information Received, Plans Issued.
|
Telephone call | | | 12/27/2006 | | |
|
|
|
Called fire alarm vendor again. Ryan Stills, Let him know we are still waiting on generator information to release fire alarm plans. (Voise Mail)
|
Telephone call | | | 12/18/2006 | | |
|
|
|
Called Ryan Stills with RFI the alarm vendor, told Ryan that I need information on the generator and fuel storage. Also if a contract for fuel delivery was in place.
|
Plan resubmittals received | | | 12/11/2006 | | |
|
|
|
|
Miscellaneous action | | | 11/16/2006 | | |
|
|
|
Faxed Copy of Failed Fire Alarm Review to RFI
|
Alarm Plan Check | 10/23/2006 | | 10/24/2006 | | FAIL |
|
|
|
Fire Alarm System Review I2 Area Bld06-00579. Fire alarm Plans submitted are not to scale. Required for review purposes.
|
Telephone call | | | 10/23/2006 | | |
|
|
|
Called Fire Alarm Applicant, Ryan Stills of RFI, in Beverton, Oregan. Left message with Ryan that the Fire Alarm Plan submitted is not to correct scale. Asked him to contact me at our office phone number. (Mike Timmerman)
|
Application received | | | 10/18/2006 | | |
|
|
|
|
Alarm Plan Check | 11/15/2006 | | | | FAIL |
|
|
|
Fire Alarm Review Assisted Living East Wing
|