INSP-Final Inspection | 12/20/2007 | 12/20/2007 | 12/20/2007 | P | PASS |
Forrest France
|
|
|
All corrections made per forest notes.KR
|
INSP-Final Inspection | 12/19/2007 | 12/20/2007 | 12/20/2007 | A | FAIL |
Forrest France
|
|
|
Heads at three locations are blocked by ceiling mounted obstructions and do not meet criteria per 8.10.6.1.2 NFPA 13 2002. UG supply flush completed okay.
|
INSP-Final Inspection | 12/18/2007 | 12/19/2007 | 12/19/2007 | P | FAIL |
Forrest France
|
|
|
No approved set of plans on site, will call this in for tomorrow to do under ground flush and final. KR
|
INSP-Final Inspection | 12/18/2007 | 12/19/2007 | 12/18/2007 | P | CANC |
Forrest France
|
|
|
Reschedule final, Brian F is the contact. Thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 12/17/2007 | 12/18/2007 | 12/18/2007 | P | NR |
Forrest France
|
|
|
According to project history, the underground supply has not yet been witnessed for flushing as required. Per phone conversation, contractor is not prepared to complete flushing today and will reschedule for tomorrow.
|
INSP-Final Inspection | 2/9/2007 | 2/12/2007 | 2/12/2007 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled when the correct outlet for flushing has been installled. No inspection was performed.
|
INSP-Supply line flush | 2/9/2007 | 2/12/2007 | 2/12/2007 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled when the outlet for the underground flush has been installed.
|
INSP-Sprinkler Rough-in | 12/14/2006 | 12/15/2006 | 12/15/2006 | A | PART |
Forrest France
|
|
|
Corrections required for OH fire sprinkler cover are complete, rough-in installation is approved for cover.
|
INSP-Sprinkler Rough-in | 12/13/2006 | 12/13/2006 | 12/14/2006 | P | FAIL |
Forrest France
|
|
|
Incorrect and missing tenting at one location, the maximum bending deflection distance exceeds the allowable amount at one room on the east side, approved plans must remain on site at all times per condition of the permit.
|
Telephone call | | | 12/12/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/12/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/28/2006 | | 12/11/2006 | | PASS |
|
|
|
Review done by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/11/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/11/2006 | | 12/11/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/28/2006 | | |
|
|
|
|
Plan assigned to (SAM) | 11/28/2006 | | 11/28/2006 | | DONE |
|
|
|
|
Miscellaneous action | | | 11/28/2006 | | DONE |
|
|
|
Approved Early Start request to install rough-in piping of residential sprinkler system, excluding the gagrage sprinklers which were omitted from the originally submitted plans.
|
Plan resubmittals received | | | 11/13/2006 | | |
|
|
|
|
Sprinkler Plan Check | | | 11/9/2006 | | FAIL |
|
|
|
Plans reviewed by B. Johnson. Review faxed to designer. Plans available to be picked up for revision.
|
Application received | | | 10/26/2006 | | |
|
|
|
|