INSP-Final Inspection | 12/12/2006 | 12/12/2006 | 12/12/2006 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 12/7/2006 | 12/8/2006 | 12/8/2006 | P | FAIL |
Troy Cobbley
|
|
|
Still need the alarm interconnections tested and the forward flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/7/2006 | 12/8/2006 | 12/8/2006 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Final Inspection | 12/6/2006 | 12/7/2006 | 12/7/2006 | P | FAIL |
Troy Cobbley
|
|
|
See previous entry made for today.
|
INSP-Sprinkler Rough-in/Hydro | 12/6/2006 | 12/7/2006 | 12/7/2006 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test is being cancelled. Not all of the tenant improvement work has been completed. There are heads missing along the east/west demizing wall and heads needing changed due to heater locations. Also on the south side shell area two upright heads are being blocked by light fixtures.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/14/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/14/2006 | | 11/14/2006 | | DONE |
|
|
|
|
Telephone call | | | 11/14/2006 | | DONE |
|
|
|
t/c w Jim Darr at TVFP ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 11/14/2006 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/14/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 11/13/2006 | | PASS |
|
|
|
Reviewed by B. Johnson
|
Application received | | | 10/26/2006 | | |
|
|
|
|
Pending Assignment by SAM | 10/26/2006 | | | | |
|
|
|
|