INSP-Final Inspection | 12/28/2006 | 12/29/2006 | 12/28/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Supply line flush | 12/27/2006 | 12/28/2006 | 12/28/2006 | A | PASS |
Troy Cobbley
|
|
|
Forward flush passed.1,180 gallons was verified through a diffuser and a play pipe. Need lid for the vault for final.
|
INSP-Sprinkler Rough-in | 12/26/2006 | 12/27/2006 | 12/27/2006 | P | PASS |
Troy Cobbley
|
|
|
Need vault cover and forward flush
|
Override - Parcel Holds | | | 12/11/2006 | | |
|
|
|
|
Issue and Print Permit | | | 12/11/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 12/11/2006 | | |
|
|
|
|
Inspection Record Card- Fire | 12/11/2006 | | 12/11/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/1/2006 | | 12/8/2006 | | PASS |
|
|
|
Plan review done by Bryan Johnson.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/8/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/1/2006 | | |
|
|
|
|
Case Summary | | | 12/1/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 11/22/2006 | | FAIL |
|
|
|
Reviewed by B. Johnson; review comments faxed to Viking. Need contract price to determine permit fee, S rogers requested from Tom Easton, Viking.
|
Case Summary | | | 11/2/2006 | | DONE |
|
|
|
|
Application received | | | 11/2/2006 | | |
|
|
|
|
Pending Assignment by SAM | 11/2/2006 | | | | |
|
|
|
|