INSP-Final Inspection | 3/22/2007 | 3/22/2007 | 3/23/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
CHANGE STATUS TO (ISS) | | | 3/22/2007 | | DONE |
|
|
|
troy picked up the permit and took to rick at western states 3/19/2007
|
INSP-Final Inspection | 3/19/2007 | 3/19/2007 | 3/19/2007 | P | PART |
Troy Cobbley
|
|
|
Hydro test for the pre-action system passed. Hangers have been attached to the bottom chord of the trusses. An engineer needs to sign off on this or the hanger need to go to the top chord.
|
Sprinkler Plan Check | 3/16/2007 | | 3/19/2007 | | PASS |
|
|
|
As-built resubmittal plans reviewed and approved by B. Johnson. Additional fee applies due to increased number of sprinkler heads.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/19/2007 | | |
|
|
|
|
Inspection Record Card- Fire | 3/19/2007 | | 3/19/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/16/2007 | | |
|
|
|
Received letter of transmittal, application, 1pg. of e-mails between Bryan Johnson and Robert Escue, copy of fire sprinkler permit, TI Remodel Cover Sheet, Fire Sprinkler Hydraulic Calcs and cover sheet (3 copies), and 3 copies of page FP-1 with product description; routed to fire plan review
|
Telephone call | | | 3/14/2007 | | DONE |
|
|
|
telcon with spk contractor re procedures for resubmitting as-builts and calc's. Okay to not resubmit data sheets that have not changed; will resubmit three sets of plans & new calc's for new design area.
|
INSP-Sprinkler Rough-in/Hydro | 3/12/2007 | 3/12/2007 | 3/12/2007 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled per Rick
|
INSP-Sprinkler Rough-in/Hydro | 3/8/2007 | 3/8/2007 | 3/9/2007 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test for the pre-action room failed
|
INSP-Sprinkler Rough-in/Hydro | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | FAIL |
Troy Cobbley
|
|
|
Above ground hydro test failed.
|
INSP-Sprinkler Rough-in | 2/6/2007 | 2/6/2007 | 2/6/2007 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for just the office areas not the pre-action area. The office areas can not be covered yet due to insulation falling from the deck and creating obstructions to the upright sprinkler heads. Also an upright needs to be added in the west restroom due to an overspacing issue. The plans need to be resubmitted to the city for approval due to the amount of additional upright heads on the pre-action system. Many of these heads are in the hydraulic remote area.
|
INSP-Conference | 12/28/2006 | 12/29/2006 | 12/29/2006 | A | DONE |
Troy Cobbley
|
|
|
Contractor will have to attach earthquake bracing to the top of the trusses, they will have to resubmit if the change the supply to the preaction system and the duct can not be treated as obstructed construction. No approved plans were on site for review.
|
Issue and Print Permit | | | 11/29/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 11/28/2006 | | PASS |
|
|
|
Reviewed by B. Johnson.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/28/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/28/2006 | | 11/28/2006 | | DONE |
|
|
|
|
Telephone call | | | 11/28/2006 | | DONE |
|
|
|
tlk to robert escue ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 11/28/2006 | | |
|
|
|
|
Application received | | | 11/9/2006 | | |
|
|
|
|
Pending Assignment by SAM | 11/9/2006 | | | | |
|
|
|
|
Pending Assignment by SAM | 3/16/2007 | | | | |
|
|
|
|