INSP-Final Inspection | 2/21/2007 | 2/22/2007 | 2/22/2007 | A | PASS |
Forrest France
|
|
|
Fire sprinkler inspection passed, permit finaled.
|
INSP-Sprinkler Rough-in | 1/31/2007 | 2/1/2007 | 2/1/2007 | A | PART |
Forrest France
|
|
|
Per field inspection by B. Johnson, OH rough-in is approved for cover.
|
INSP-Final Inspection | 1/8/2007 | 1/9/2007 | 1/9/2007 | A | PART |
Forrest France
|
|
|
The south half of the permitted work scope area is completed and approved, final pending completion of the north half or "phase two" of the project.
|
INSP-Sprinkler Rough-in | 12/11/2006 | 12/11/2006 | 12/11/2006 | P | PART |
Forrest France
|
|
|
OH sprinkler rough-in is good for cover at the drop ceilings in the areas as noted on approved plan set.
|
Issue and Print Permit | | | 11/29/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/27/2006 | | 11/27/2006 | | DONE |
|
|
|
|
Telephone call | | | 11/27/2006 | | DONE |
|
|
|
left vm w Brad Bettencourt at SimplexGrinnell ###-#### - permit ready and fees given ($150.00)
|
Permit Ready to Issue | | | 11/27/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 11/24/2006 | | PASS |
|
|
|
Reviewed by B. Johnson
|
Case Summary | | | 11/14/2006 | | |
|
|
|
|
Application received | | | 11/14/2006 | | |
|
|
|
|
Pending Assignment by SAM | 11/14/2006 | | | | |
|
|
|
|