INSP-Final Inspection | 1/30/2007 | 1/31/2007 | 1/31/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled. forward flush passed and the heads have been added at the columns located within the racking.
|
INSP-Final Inspection | 1/25/2007 | 1/26/2007 | 1/26/2007 | P | CANC |
Troy Cobbley
|
|
|
Not ready for inspection
|
INSP-Sprinkler Rough-in/Hydro | 1/25/2007 | 1/26/2007 | 1/26/2007 | A | PASS |
Troy Cobbley
|
|
|
hydro test passed. system held 210 lbs for 2 hours. sprinkler rough-in passed except column protection is required. Also still need tags, signs and forward flush
|
INSP-Sprinkler Rough-in/Hydro | 1/24/2007 | 1/25/2007 | 1/25/2007 | A | CANC |
Troy Cobbley
|
|
|
Apparently the wrong permit was called in since the contact person did not know about inspection
|
INSP-Sprinkler Rough-in/Hydro | 1/23/2007 | 1/24/2007 | 1/24/2007 | P | CANC |
Forrest France
|
|
|
contact: Jason Hord - OH Hydro Test Phone #: ###-#### x1234
|
Issue and Print Permit | | | 12/5/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/4/2006 | | 12/4/2006 | | DONE |
|
|
|
|
Telephone call | | | 12/4/2006 | | DONE |
|
|
|
t/c w Liz at DeBest Fire ###-#### - permit ready and fees given ($158.76)
|
Permit Ready to Issue | | | 12/4/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/1/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/20/2006 | | 11/29/2006 | | PASS |
|
|
|
Reviewed by B. Johnson
|
Application received | | | 11/20/2006 | | |
|
|
|
|
Pending Assignment by SAM | 11/20/2006 | | | | |
|
|
|
|