Case Summary | | | 11/13/2007 | | |
|
|
|
|
INSP-Final Inspection | 2/2/2007 | 2/5/2007 | 2/5/2007 | P | PASS |
Forrest France
|
|
|
Fire sprinkler passed final field inspection, contractor to provide missing "911"sign at the outside bell as discussed.
|
INSP-Final Inspection | 2/1/2007 | 2/2/2007 | 2/2/2007 | P | DEFR |
Forrest France
|
|
|
Inspection to be completed in conjunction with the FA permit on 2/5 as scheduled.
|
INSP-Sprinkler Rough-in/Hydro | 1/31/2007 | 2/1/2007 | 2/1/2007 | P | PART |
Forrest France
|
|
|
Per field inspection by B. Johnson, the overhead fire sprinkler rough-in including the booster pump and holding tank are acceptable.
|
Issue permit | | | 12/18/2006 | | |
|
|
|
|
Sprinkler Plan Check | 11/28/2006 | | 12/14/2006 | | PASS |
|
|
|
Plan review done by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2006 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/14/2006 | | 12/14/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/14/2006 | | DONE |
|
|
|
|
Telephone call | | | 12/14/2006 | | DONE |
|
|
|
tlk to jim danes ###-#### that permit and fees are ready to be picked up
|
Case Summary | | | 11/28/2006 | | DONE |
|
|
|
|
Application received | | | 11/28/2006 | | |
|
|
|
|
Pending Assignment by SAM | 11/28/2006 | | | | |
|
|
|
|