INSP-Final Inspection | 3/8/2007 | 3/8/2007 | 3/8/2007 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/7/2007 | 3/8/2007 | 3/8/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro passed. Calculation sticker and flexible couplings installed.
|
INSP-Final Inspection | 3/6/2007 | 3/7/2007 | 3/7/2007 | P | FAIL |
Troy Cobbley
|
|
|
provide flexible couplings at the top and bottom of the riser and provide hydraulic sticker for the rise
|
INSP-Final Inspection | 3/5/2007 | 3/6/2007 | 3/6/2007 | P | CANC |
Troy Cobbley
|
|
|
waiting on fire alarm
|
INSP-Sprinkler Rough-in/Hydro | 3/1/2007 | 3/1/2007 | 3/2/2007 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed. This includes the anti-freeze loop.
|
INSP-Supply line flush | 2/15/2007 | 2/16/2007 | 2/16/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in | 1/29/2007 | 1/30/2007 | 1/30/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground piping is ok to cover
|
Telephone call | | | 1/24/2007 | | DONE |
|
|
|
Telcon from "Mick" of Western Fire Protection-regarding the lack of prescribed depth of bury of a section of UG. He proposed two alt's: covering pipe with foam and putting a speed bump over the trench, instead of adding 4 el's to drop the pipe/trench depth to prescribed depth. I indicated we would consider either of his proposed alt's if the design were prepared and stamped, with supporting calc's showing the alt design would have the equivalent insulating value as the prescribed method. He will investigate the 3 options further before making a decision.
|
INSP-Supply line flush | 1/22/2007 | 1/22/2007 | 1/22/2007 | P | FAIL |
Troy Cobbley
|
|
|
This was for an underground inspection.The underground supply piping is not buried below 4'-6" as required. Top of pipe is at 3'-10"
|
INSP-Sprinkler Rough-in | 12/20/2006 | 12/21/2006 | 12/21/2006 | A | PART |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover but some items have not been corrected. See city approved plans for the redlined items.
|
INSP-Sprinkler Rough-in | 12/15/2006 | 12/18/2006 | 12/18/2006 | P | FAIL |
Troy Cobbley
|
|
|
Pipe sizes as shown on the plans, in the locations marked, do not match the piping as installed. Pipe needs to be changed or these changes need to be proven with revised hydraulic calculations when the as-builts are resubmitted as per the review comments. There are other deficiencies also marked on the plans. Piping is not to be covered.
|
Inspection Record Card- Fire | 12/15/2006 | | 12/15/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/15/2006 | | DONE |
|
|
|
|
Telephone call | | | 12/15/2006 | | DONE |
|
|
|
tlk to mick in boise and let him that permit and fees are ready to be picked up
|
Issue and Print Permit | | | 12/15/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/1/2006 | | 12/14/2006 | | PASS |
|
|
|
Plan review done by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2006 | | DONE |
|
|
|
|
Application received | | | 12/1/2006 | | |
|
|
|
|
Pending Assignment by SAM | 12/1/2006 | | | | |
|
|
|
|