INSP-Final Inspection | 10/2/2007 | 10/3/2007 | 10/3/2007 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Issue permit | | | 9/25/2007 | | |
|
|
|
|
INSP-Final Inspection | 9/21/2007 | 9/24/2007 | 9/24/2007 | A | CANC |
Troy Cobbley
|
|
|
Cancelled due to alarm panel problems.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/24/2007 | | 9/24/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/24/2007 | | DONE |
|
|
|
tlk to dennis skiner ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 9/24/2007 | | DONE |
|
|
|
|
INSP-Final Inspection | 9/20/2007 | 9/21/2007 | 9/21/2007 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection covered reinspecting the blocked sprinkler heads through out the building. The only areas not inspected for blockage are the 1st and 2nd floors of D wing.
|
INSP-Final Inspection | 9/20/2007 | 9/20/2007 | 9/20/2007 | P | CANC |
Troy Cobbley
|
|
|
Overbooked with Micron plan review.
|
Sprinkler Plan Check | 9/5/2007 | | 9/20/2007 | | PASS |
|
|
|
As--built plans are approved 09/20/2007 by Bryan Johnson
|
INSP-Final Inspection | 9/17/2007 | 9/19/2007 | 9/19/2007 | P | CANC |
Troy Cobbley
|
|
|
gilbert was not ready for inspection when I was there with Mike and Ken.
|
INSP-Final Inspection | 9/5/2007 | 9/6/2007 | 9/6/2007 | A | FAIL |
Troy Cobbley
|
|
|
I inspected the second floor wings D, C and B. As with the previous inspection many pendants are blocked and the electrical room is missing coverage. I stopped the inspection until all of blocked heads have been fixed.
|
INSP-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 | A | FAIL |
Troy Cobbley
|
|
|
The remaining 3rd floor areas were inspected. The same obstructions as noted yesterday occur in the other third floor areas. There was no access into room 397. A canopy was missing from the bathroom pendant in room 374 and no sprinkler coverage was provided in the corridor electrical closet on the third floor C wing. The items from the previous correction notice still need addressed.
|
Plan resubmittals received | | | 9/5/2007 | | |
|
|
|
|
INSP-Final Inspection | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | FAIL |
Troy Cobbley
|
|
|
The final inspecton for the third floor of A wing was started today. I found that instead of viking pendants being installed reliable pendants had been installed. Also many of the light fixtures are blocking the pendant heads in the laundry/utility romms and in the main corridor.
|
INSP-Conference | 8/27/2007 | 8/27/2007 | 8/27/2007 | P | DONE |
Troy Cobbley
|
|
|
I spoke to Katie about the occupancy load signs and their locations.
|
Inspection Record Card- Fire | 6/19/2007 | | 7/2/2007 | | |
|
|
|
|
Plan resubmittals received | | | 6/19/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2007 | | DONE |
|
|
|
|
Telephone call | | | 3/8/2007 | | DONE |
|
|
|
tlk to fire protection ###-#### that permit is ready to be picked up
|
Permit Ready to Issue | | | 3/8/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/8/2007 | | 3/8/2007 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/8/2007 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/8/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/6/2007 | | 3/7/2007 | | PASS |
|
|
|
Plans are approved per attached findings per Bryan Johnson
|
Plan resubmittals received | | | 3/6/2007 | | |
|
|
|
plans sent directly to B. Johnson by contractor; relocation of proposed wall FDC to a yard area.
|
INSP-Sprinkler Rough-in | 2/20/2007 | 2/21/2007 | 2/22/2007 | A | PASS |
Troy Cobbley
|
|
|
Inspection was for building C. Rough to cover for third floor passed, Attic/dry system pipe passed, first and second floor main piping EQ restraints and hanger assemblies passed, first and second floor rough to cover passed. The FDC location is in question. Brian asked the general/Dale to supply PDS with a new proposed layout for review.
|
INSP-Sprinkler Rough-in/Hydro | 1/31/2007 | 2/2/2007 | 2/2/2007 | A | PASS |
Troy Cobbley
|
|
|
hydro tests for 1st, 2nd and 3rd floors of the north wing passed. These were witnessed by the superintendant dale shuart
|
Issue and Print Permit | | | 1/24/2007 | | DONE |
|
|
|
|
Case Summary | | | 1/19/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2007 | | PASS |
|
|
|
|
Inspection Record Card- Fire | 1/19/2007 | | 1/19/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/19/2007 | | DONE |
|
|
|
|
Telephone call | | | 1/19/2007 | | DONE |
|
|
|
tlk to dennis skinner ###-#### that permit and fees are ready to be picked up
|
Sprinkler Plan Check | 1/9/2007 | | 1/16/2007 | | PASS |
|
|
|
Plan review by Bryan Johnson
|
Plan resubmittals received | | | 1/9/2007 | | |
|
|
|
|
Sprinkler Plan Check | 12/18/2006 | | 12/20/2006 | | FAIL |
|
|
|
denied 12/18/2006 plans retained by Bryan Johnson
|
Plan resubmittals received | | | 12/4/2006 | | |
|
|
|
Received page 1 of 16 and 4 sets of hydraulic calculations; taken to Sam Rogers
|
Application received | | | 12/1/2006 | | |
|
|
|
|
Pending Assignment by SAM | 12/1/2006 | | | | |
|
|
|
|