INSP-Final Inspection | 10/2/2007 | 10/3/2007 | 10/3/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
CHANGE STATUS TO (ISS) | | | 9/25/2007 | | |
|
|
|
already issued
|
INSP-Final Inspection | 9/21/2007 | 9/24/2007 | 9/24/2007 | A | CANC |
Troy Cobbley
|
|
|
Cancelled due to alarm panel problems.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/24/2007 | | 9/24/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/24/2007 | | DONE |
|
|
|
tlk to dennis skiner ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 9/24/2007 | | DONE |
|
|
|
|
INSP-Final Inspection | 9/20/2007 | 9/21/2007 | 9/21/2007 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection covered reinspecting the blocked sprinkler heads through out the building. The only areas not inspected for blockage are the 1st and 2nd floors of D wing.
|
INSP-Final Inspection | 9/20/2007 | 9/20/2007 | 9/20/2007 | P | CANC |
Troy Cobbley
|
|
|
Overbooked with Micron plan review.
|
Sprinkler Plan Check | 9/5/2007 | | 9/20/2007 | | PASS |
|
|
|
As---built Plans are approved 09/20/2007 by Bryan Johnson
|
INSP-Final Inspection | 9/17/2007 | 9/18/2007 | 9/18/2007 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection covered the modified sprinkler heads in "A" wing 1st, 2nd and 3rd floors. They all look good except for one head was missed in the southwest third floor stairwell ceiling and in the common electrical room that is on all floors.
|
INSP-Final Inspection | 9/5/2007 | 9/6/2007 | 9/6/2007 | A | FAIL |
Troy Cobbley
|
|
|
I inspected the second floor wings D, C and B. As with the previous inspection many pendants are blocked and the electrical room is missing coverage. I stopped the inspection until all of blocked heads have been fixed.
|
INSP-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 | A | FAIL |
Troy Cobbley
|
|
|
The remaining 3rd floor areas were inspected. The same obstructions as noted yesterday occur in the other third floor areas. There was no access into room 397. A canopy was missing from the bathroom pendant in room 374 and no sprinkler coverage was provided in the corridor electrical closet on the third floor C wing. The items from the previous correction notice still need addressed.
|
Plan resubmittals received | | | 9/5/2007 | | |
|
|
|
|
INSP-Final Inspection | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | FAIL |
Troy Cobbley
|
|
|
The final inspecton for the third floor of A wing was started today. I found that instead of viking pendants being installed reliable pendants had been installed. Also many of the light fixtures are blocking the pendant heads in the laundry/utility romms and in the main corridor.
|
INSP-Sprinkler Rough-in | 6/25/2007 | 6/26/2007 | 6/27/2007 | P | PASS |
Troy Cobbley
|
|
|
I inspected Bldg. D attic piping today. There were a few problems with bracing, the problems were corrected by the end of the inspection. I also witnessed the hydro test for the attic piping and second floor of the same bldg. The hydro went fine.
|
INSP-Sprinkler Rough-in/Hydro | 6/22/2007 | 6/25/2007 | 6/25/2007 | A | CANC |
Troy Cobbley
|
|
|
gilbert; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
Plan resubmittals received | | | 6/19/2007 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 5/29/2007 | 5/31/2007 | 5/31/2007 | A | PASS |
Troy Cobbley
|
|
|
The second floor of building D rough to cover is passed as well as the second floor hydro test
|
INSP-Sprinkler Rough-in/Hydro | 5/18/2007 | 5/21/2007 | 5/21/2007 | P | PASS |
Troy Cobbley
|
|
|
The first floor of area "D" is ok to cover except for the areas where the attic system needs to be installed. Per the general contractor there are support issues with the light weight trusses that are being worked out with the structural engineer.
|
INSP-Sprinkler Rough-in | 2/7/2007 | 2/9/2007 | 2/9/2007 | A | CANC |
Troy Cobbley
|
|
|
Inspection performed yesterday by Brian Johnson
|
INSP-Sprinkler Rough-in | 2/7/2007 | 2/8/2007 | 2/8/2007 | A | PART |
Troy Cobbley
|
|
|
First and second floors of the C wing are ok to cover. Third floor can not be covered yet. See city approved plans for the corrections required.
|
INSP-Sprinkler Rough-in | 2/5/2007 | 2/6/2007 | 2/6/2007 | A | PART |
Troy Cobbley
|
|
|
The second floor of C wing will be ok to cover when the insulation is installed between the walls and the drop downs to the dry sidewalls. Also one pendant is overspaced as marked on the plans. C wing attic dry system 200 lb hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/2/2007 | 2/5/2007 | 2/5/2007 | A | PASS |
Troy Cobbley
|
|
|
First floor of the C wing rough-in piping was completed today. Contractor needs to provide verification from truss manufacturer for the mounting of the eq bracing and the hanging of the 3" main.
|
Issue and Print Permit | | | 1/24/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2007 | | PASS |
|
|
|
|
Inspection Record Card- Fire | 1/19/2007 | | 1/19/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/19/2007 | | DONE |
|
|
|
|
Telephone call | | | 1/19/2007 | | DONE |
|
|
|
tlk to dennis skinner ###-#### that permit and fees are ready to be picked up
|
Sprinkler Plan Check | 1/9/2007 | | 1/16/2007 | | PASS |
|
|
|
Plan review by Bryan Johnson
|
Plan resubmittals received | | | 1/9/2007 | | |
|
|
|
|
Sprinkler Plan Check | 12/4/2006 | | 12/18/2006 | | FAIL |
|
|
|
plans retained by Bryan Johnson
|
Plan resubmittals received | | | 12/4/2006 | | |
|
|
|
Received page 1 of 16 and 4 sets of hydraulic calculations; taken to Sam Rogers
|
Application received | | | 12/1/2006 | | |
|
|
|
|
Pending Assignment by SAM | 12/1/2006 | | | | |
|
|
|
|
Inspection Record Card- Fire | 9/24/2007 | | | | |
|
|
|
|