INSP-Final Inspection | 9/24/2007 | 9/25/2007 | 9/25/2007 | P | PASS |
Troy Cobbley
|
|
|
gilbert - ###-####
|
CHANGE STATUS TO (ISS) | | | 9/25/2007 | | |
|
|
|
already issued previosly
|
INSP-Final Inspection | 9/21/2007 | 9/24/2007 | 9/24/2007 | A | CANC |
Troy Cobbley
|
|
|
Cancelled due to alarm panel problems.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/24/2007 | | 9/24/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/24/2007 | | |
|
|
|
tlk to dennis skiner ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 9/24/2007 | | DONE |
|
|
|
|
INSP-Final Inspection | 9/20/2007 | 9/21/2007 | 9/21/2007 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection covered reinspecting the blocked sprinkler heads through out the building. The only areas not inspected for blockage are the 1st and 2nd floors of D wing.
|
INSP-Final Inspection | 9/20/2007 | 9/20/2007 | 9/20/2007 | P | CANC |
Troy Cobbley
|
|
|
Overbooked with Micron plan review.
|
Sprinkler Plan Check | 9/5/2007 | | 9/20/2007 | | PASS |
|
|
|
As--built Plans are approved 09/20/2007 by Bryan Johnson
|
INSP-Final Inspection | 9/17/2007 | 9/19/2007 | 9/19/2007 | P | CANC |
Troy Cobbley
|
|
|
gilbert was not ready for inspection when I was there with Mike and Ken.
|
INSP-Final Inspection | 9/17/2007 | 9/17/2007 | 9/17/2007 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for the blocked pendant heads. I found more heads in the first location I looked on the third floor so I ended the inspection
|
INSP-Final Inspection | 9/5/2007 | 9/6/2007 | 9/6/2007 | A | FAIL |
Troy Cobbley
|
|
|
I inspected the second floor wings D, C and B. As with the previous inspection many pendants are blocked and the electrical room is missing coverage. I stopped the inspection until all of blocked heads have been fixed.
|
INSP-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 | A | FAIL |
Troy Cobbley
|
|
|
The remaining 3rd floor areas were inspected. The same obstructions as noted yesterday occur in the other third floor areas. There was no access into room 397. A canopy was missing from the bathroom pendant in room 374 and no sprinkler coverage was provided in the corridor electrical closet on the third floor C wing. The items from the previous correction notice still need addressed.
|
Plan resubmittals received | | | 9/5/2007 | | |
|
|
|
|
INSP-Final Inspection | 8/31/2007 | 9/4/2007 | 9/4/2007 | | FAIL |
Troy Cobbley
|
|
|
The final inspecton for the third floor of A wing was started today. I found that instead of viking pendants being installed reliable pendants had been installed. Also many of the light fixtures are blocking the pendant heads in the laundry/utility romms and in the main corridor. Need to change out heads or resubmit as built plans and data sheets for verification of hydraulic calcs and head spacing. Also need data sheets for the dry s/w heads to verify installation distance below ceilings on patios.
|
Telephone call | | | 9/4/2007 | | DONE |
|
|
|
telcon from Dennis Skinner requesting an OTC review of plans and hydraulic calc's using the differnet heads they installed in residential units. I indicated we do not have an OTC review capability and plans need to be reviewed for hydraulics as well as head spacing per the data sheet for the new head. We cannot give the plans priority ahead of other resubmittals due to the volume of our current workload but we will can fit them in ASAP while meeting our time commitments to other plans already in line. Meantime, I willl ask Troy to continue inspections using the current on-site approved plan set as long as the only change is this head replacement wherever such heads are shown on plans and they provide mfg's data sheets on site to verify installation rules.
|
INSP-Supply line flush | 7/16/2007 | 7/17/2007 | 7/17/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2007 | 7/3/2007 | 7/5/2007 | P | PASS |
Troy Cobbley
|
|
|
I finished a hydro and overhead rough to cover inspection at Bonaventure Bldg. B
|
Sprinkler Plan Check | 6/19/2007 | | 7/2/2007 | | PASS |
|
|
|
*As---built plans are approved 07/02/2007 by Bryan Johnson
|
INSP-Sprinkler Rough-in/Hydro | 6/26/2007 | 6/27/2007 | 6/28/2007 | P | PASS |
Troy Cobbley
|
|
|
The hydro for the Attic main piping and second floor passed. There were some brace issues that were remedied by the end of the inspection. The intermediate area above the kitchen is being sprinkler because the owner didn’t want to insulate as originally agreed upon. The plans for that revision have been submitted to Brian.
|
INSP-Sprinkler Rough-in | 6/25/2007 | 6/26/2007 | 6/27/2007 | P | CANC |
Troy Cobbley
|
|
|
This part of the project was not ready for inspection.
|
INSP-Sprinkler Rough-in/Hydro | 6/22/2007 | 6/25/2007 | 6/25/2007 | P | CANC |
Troy Cobbley
|
|
|
gilbert; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang Inspection cancelled from web by: Patricia Smith
|
Plan resubmittals received | | | 6/19/2007 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 6/6/2007 | 6/7/2007 | 6/7/2007 | A | PASS |
Troy Cobbley
|
|
|
Third floor tenting passed.
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2007 | 6/4/2007 | 6/5/2007 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed for central building.
|
INSP-Sprinkler Rough-in/Hydro | 5/29/2007 | 6/1/2007 | 6/4/2007 | A | PART |
Troy Cobbley
|
|
|
Attic and third floor piping rough in is passed but a tenting inspection is still needed per brian and the hydro test failed.
|
INSP-Sprinkler Rough-in | 5/10/2007 | 5/11/2007 | 5/11/2007 | A | PASS |
Troy Cobbley
|
|
|
Area A attic system is ok to cover.
|
Issue and Print Permit | | | 5/10/2007 | | DONE |
|
|
|
|
Case Summary | | | 5/9/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/30/2007 | | 5/9/2007 | | PASS |
|
|
|
Plans are approved w/attached comments by bryan johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/9/2007 | | 5/9/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/9/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/9/2007 | | |
|
|
|
tlk to dennis skinner ###-#### that 3rd review and fees are ready to be picked up
|
Plan resubmittals received | | | 4/30/2007 | | |
|
|
|
Received by mail transmittal sheet, 1pg. letter to plan reviewer, fire sprinkler application, copy of fire sprinkler license certificate, 6 copies of 2pg.hydraulic calculations, six copies of page 12 of 16 for bldg 'A' and three copies of page 5 of 16 for bldg 'C' ;routed to fire plan review
|
INSP-Sprinkler Rough-in | 4/20/2007 | 4/23/2007 | 4/24/2007 | P | PASS |
Troy Cobbley
|
|
|
Third floor wet system and dry system hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2007 | 3/14/2007 | 3/15/2007 | P | PASS |
Troy Cobbley
|
|
|
The remaining underground supply and FDC piping is ok to cover. Both passed their hydro testes
|
INSP-Sprinkler Rough-in | 3/12/2007 | 3/13/2007 | 3/13/2007 | A | PASS |
Troy Cobbley
|
|
|
The underground supply and the supply to the remote FDC is ok to bury from the building up to within 30'-0" of where the FDC is to be located. The second floor of A wing is ok to cover except the earthquake bracing on the 3" mains is not complete.
|
INSP-Sprinkler Rough-in/Hydro | 3/8/2007 | 3/9/2007 | 3/9/2007 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test of the first and second floors of building A have passed. The first floor of building A is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground supply and the remote FDC piping is ok to cover from the stub out to 15' past the patio
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2007 | 2/28/2007 | 3/1/2007 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for a partial on the underground supply line and remote FDC. Both pipes from the stub out to roughly twenty feet were not at the required bury depth of 4'6". The only piping in the trench was the twenty feet. Also the new FDC location has not been approved yet
|
Issue and Print Permit | | | 2/15/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/2/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/2/2007 | | DONE |
|
|
|
|
Telephone call | | | 2/2/2007 | | |
|
|
|
tlk to secretary for dennis skinner ###-#### that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 2/2/2007 | | 2/2/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/24/2007 | | 1/31/2007 | | PASS |
|
|
|
Plan review by Bryan Johnson approved w/conditions 1/31/2007
|
Plan resubmittals received | | | 1/24/2007 | | |
|
|
|
ok to take in per Scott A.
|
Plan resubmittals received | | | 1/9/2007 | | |
|
|
|
|
Sprinkler Plan Check | 12/4/2006 | | 12/18/2006 | | FAIL |
|
|
|
denied 12/18/2006 plans retained by Bryan Johnson
|
Plan resubmittals received | | | 12/4/2006 | | |
|
|
|
Received page 1 of 16 and 4 sets of hydraulic calculations; taken to Sam Rogers
|
Application received | | | 12/1/2006 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 5/9/2007 | 5/10/2007 | | P | |
|
|
|
gilbert - ###-####
|
Inspection Record Card- Fire | 5/9/2007 | | | | |
|
|
|
|
Pending Assignment by SAM | 12/1/2006 | | | | |
|
|
|
|