INSP-Final Inspection | 2/21/2008 | 2/22/2008 | 2/22/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Forward flush passed.
|
Inspection Record Card- Fire | 2/22/2008 | | 2/22/2008 | | DONE |
Patricia Smith
|
|
|
jeff packham called in and asked for another inspection record card 2-22-08ps
|
INSP-Sprinkler Rough-in/Hydro | 10/18/2007 | 10/19/2007 | 10/19/2007 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed
|
INSP-Sprinkler Rough-in | 10/17/2007 | 10/18/2007 | 10/18/2007 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test started at 8:00 with 41 1/4 lbs
|
INSP-Sprinkler Rough-in/Hydro | 10/16/2007 | 10/17/2007 | 10/17/2007 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Supply line flush | 9/27/2007 | 9/28/2007 | 9/28/2007 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line flush for the building is passed. I also gave a rough-in inspection for the overhead piping that Forrest had not looked at. This piping is ok.
|
INSP-Sprinkler Rough-in/Hydro | 9/20/2007 | 9/21/2007 | 9/21/2007 | A | PASS |
Troy Cobbley
|
|
|
The underground flush for the future supply, located to the west of the new building has passed.
|
INSP-Supply line flush | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | FAIL |
Troy Cobbley
|
|
|
Arrived at the job site but the contractor was not there. Needs to be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 9/12/2007 | 9/12/2007 | 9/12/2007 | P | PASS |
Troy Cobbley
|
|
|
The underground hydro test passed for both lines.
|
INSP-Sprinkler Rough-in/Hydro | 9/10/2007 | 9/10/2007 | 9/11/2007 | P | FAIL |
Troy Cobbley
|
|
|
The underground supply line blew a seal and will need to be dug up and repaired.
|
INSP-Sprinkler Rough-in | 5/23/2007 | 5/24/2007 | 5/24/2007 | P | PART |
Forrest France
|
|
|
UG fire supply line install matches approved plans-okay to bury, also inspected three rooms with hard lid ceilings as circled and initialed on stamped plans okay for cover.
|
INSP-Sprinkler Rough-in | 3/21/2007 | 3/22/2007 | 3/22/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground stub-in only is ok to bury.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/8/2007 | | 3/8/2007 | | DONE |
|
|
|
|
Telephone call | | | 3/8/2007 | | DONE |
|
|
|
tlk to jeff packham ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 3/8/2007 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/8/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/26/2007 | | 3/7/2007 | | PASS |
|
|
|
*As built Plans & Calculation are approved by Bryan Johnson
|
Plan resubmittals received | | | 2/26/2007 | | |
|
|
|
|
Sprinkler Plan Check | 2/14/2007 | | 2/16/2007 | | FAIL |
|
|
|
plan denied by Bryan Johnson
|
Plan resubmittals received | | | 2/6/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/14/2006 | | 12/28/2006 | | FAIL |
|
|
|
Plan review denied by Bryan Johnson
|
Application received | | | 12/14/2006 | | |
|
|
|
|
Pending Assignment by SAM | 12/14/2006 | | | | |
|
|
|
|