Permit Information
Permit NumberFIR06-00988
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 12877 W MCMILLAN RD
Project Name 
Customer Number 
ePlanReview 
Description
To construct a 6,673 sq. ft. Type IIB one story addition to the existing Verizon switch gear office building and to remodel the interior of the existing building. This building is to be fully fire sprinkled. Sprinklers used for area increase. The existing underground supply piping with be abandoned. A new 6” lead in will be installed.
The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD06-00749
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/21/20082/22/20082/22/2008APASS
DetailsTroy Cobbley
Permit finaled. Forward flush passed.
Inspection Record Card- Fire2/22/2008 2/22/2008 DONE
DetailsPatricia Smith
jeff packham called in and asked for another inspection record card 2-22-08ps
INSP-Sprinkler Rough-in/Hydro10/18/200710/19/200710/19/2007APASS
DetailsTroy Cobbley
24 hour air test passed
INSP-Sprinkler Rough-in10/17/200710/18/200710/18/2007APASS
DetailsTroy Cobbley
24 hour air test started at 8:00 with 41 1/4 lbs
INSP-Sprinkler Rough-in/Hydro10/16/200710/17/200710/17/2007APASS
DetailsTroy Cobbley
Above ground hydro test passed.
INSP-Supply line flush9/27/20079/28/20079/28/2007APASS
DetailsTroy Cobbley
The underground supply line flush for the building is passed. I also gave a rough-in inspection for the overhead piping that Forrest had not looked at. This piping is ok.
INSP-Sprinkler Rough-in/Hydro9/20/20079/21/20079/21/2007APASS
DetailsTroy Cobbley
The underground flush for the future supply, located to the west of the new building has passed.
INSP-Supply line flush9/19/20079/20/20079/20/2007AFAIL
DetailsTroy Cobbley
Arrived at the job site but the contractor was not there. Needs to be rescheduled.
INSP-Sprinkler Rough-in/Hydro9/12/20079/12/20079/12/2007PPASS
DetailsTroy Cobbley
The underground hydro test passed for both lines.
INSP-Sprinkler Rough-in/Hydro9/10/20079/10/20079/11/2007PFAIL
DetailsTroy Cobbley
The underground supply line blew a seal and will need to be dug up and repaired.
INSP-Sprinkler Rough-in5/23/20075/24/20075/24/2007PPART
DetailsForrest France
UG fire supply line install matches approved plans-okay to bury, also inspected three rooms with hard lid ceilings as circled and initialed on stamped plans okay for cover.
INSP-Sprinkler Rough-in3/21/20073/22/20073/22/2007APASS
DetailsTroy Cobbley
Underground stub-in only is ok to bury.
PLANS/APPL TAKEN TO FRONT DESK  3/8/2007 DONE
Inspection Record Card- Fire3/8/2007 3/8/2007 DONE
Telephone call  3/8/2007 DONE
tlk to jeff packham ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  3/8/2007 DONE
Issue and Print Permit  3/8/2007 DONE
Sprinkler Plan Check2/26/2007 3/7/2007 PASS
*As built Plans & Calculation are approved by Bryan Johnson
Plan resubmittals received  2/26/2007  
Sprinkler Plan Check2/14/2007 2/16/2007 FAIL
plan denied by Bryan Johnson
Plan resubmittals received  2/6/2007 DONE
Sprinkler Plan Check12/14/2006 12/28/2006 FAIL
Plan review denied by Bryan Johnson
Application received  12/14/2006  
Pending Assignment by SAM12/14/2006